(1)Subsection (2) below applies where a licence holder makes an application to the Secretary of State for his consent under section 36 above for the construction or extension of a generating station and, for a purpose connected with the proposed construction or extension of that station, makes either or both of the following, namely—
(a)a compulsory purchase order; and
(b)an application to the Secretary of State for authorisation under paragraph 1 of Schedule 5 to this Act (water rights for hydro-electric generating stations in Scotland).
(2)The proceedings which—
(a)in the case of a compulsory purchase order, are required by Part II of the M1Acquisition of Land Act 1981 or Schedule 1 to the M2Acquisition of Land (Authorisation Procedure) (Scotland) Act 1947 to be taken for the purpose of confirming that order;
(b)in the case of an application under paragraph 1 of Schedule 5 to this Act, are required by paragraphs 7 to 12 of that Schedule to be taken in relation to that application,
may be taken concurrently (so far as practicable) with the proceedings required by Schedule 8 to this Act to be taken in relation to the application for consent under section 36 above.
(3)Subsection (4) below applies where a licence holder makes an application to the Secretary of State for his consent under section 37 above for the installation of an electric line above ground and, for a purpose connected with the proposed installation of that line, makes one or more of the following, namely—
(a)a compulsory purchase order;
(b)an application to the Secretary of State under paragraph 6 of Schedule 4 to this Act for a necessary wayleave; and
(c)a reference to the Secretary of State under paragraph 9 (felling and lopping of trees) of that Schedule.
(4)The proceedings which—
(a)in the case of a compulsory purchase order, are required by Part II of the Acquisition of Land Act 1981 or Schedule 1 to the Acquisition of Land (Authorisation Procedure) (Scotland) Act 1947 to be taken for the purpose of confirming that order;
(b)in the case of an application under paragraph 6 of Schedule 4 to this Act, are required by that paragraph to be taken in relation to that application;
(c)in the case of a reference under paragraph 9 of that Schedule, are required by that paragraph to be taken in relation to that reference,
may be taken concurrently (so far as practicable) with the proceedings required by Schedule 8 to this Act to be taken in relation to the application for consent under section 37 above.
(5)Where, for a purpose connected with the proposed installation of an electric line, a licence holder makes—
(a)an application to the Secretary of State under paragraph 6 of Schedule 4 to this Act for the necessary wayleave; and
(b)a reference to the Secretary of State under paragraph 9 of that Schedule,
the proceedings required by the said paragraph 9 to be taken in relation to the reference under that paragraph may be taken concurrently (so far as practicable) with the proceedings required by the said paragraph 6 to be taken in relation to the application under that paragraph.