Part IU.K. ELECTRICITY SUPPLY

Modifications etc. (not altering text)

C2Pt. I (ss. 1-64) applied (1.10.2001) by S.I. 2001/3264, regs. 4(2), 5(2)

C3Pt. I (ss. 1-64) amended (E.W.) (27.10.2000) by S.I. 2000/2727, art. 10

Pt. I (ss. 1-64) amended (7.11.2000) by 2000 c. 27, s. 105(1)(a); S.I. 2000/2974, art. 2, Sch. (subject to transitional provisions in arts. 3-12)

Pt. I (ss. 1-64) amended (E.W.) (1.10.2001) by S.I. 2000/2727, art. 10 (as substituted (1.10.2001) by S.I. 2001/3268, art. 2(13))

SupplementalE+W+S

61 Concurrent proceedings.E+W+S

(1)Subsection (2) below applies where a licence holder makes an application to the Secretary of State for his consent under section 36 above for the construction or extension of a generating station and, for a purpose connected with the proposed construction or extension of that station, makes either or both of the following, namely—

(a)a compulsory purchase order; and

(b)an application to the Secretary of State for authorisation under paragraph 1 of Schedule 5 to this Act (water rights for hydro-electric generating stations in Scotland).

(2)The proceedings which—

(a)in the case of a compulsory purchase order, are required by Part II of the M1Acquisition of Land Act 1981 or Schedule 1 to the M2Acquisition of Land (Authorisation Procedure) (Scotland) Act 1947 to be taken for the purpose of confirming that order;

(b)in the case of an application under paragraph 1 of Schedule 5 to this Act, are required by paragraphs 7 to 12 of that Schedule to be taken in relation to that application,

may be taken concurrently (so far as practicable) with the proceedings required by Schedule 8 to this Act to be taken in relation to the application for consent under section 36 above.

(3)Subsection (4) below applies where a licence holder makes an application to the Secretary of State for his consent under section 37 above for the installation of an electric line above ground and, for a purpose connected with the proposed installation of that line, makes one or more of the following, namely—

(a)a compulsory purchase order;

(b)an application to the Secretary of State under paragraph 6 of Schedule 4 to this Act for a necessary wayleave; and

(c)a reference to the Secretary of State under paragraph 9 (felling and lopping of trees) of that Schedule.

(4)The proceedings which—

(a)in the case of a compulsory purchase order, are required by Part II of the Acquisition of Land Act 1981 or Schedule 1 to the Acquisition of Land (Authorisation Procedure) (Scotland) Act 1947 to be taken for the purpose of confirming that order;

(b)in the case of an application under paragraph 6 of Schedule 4 to this Act, are required by that paragraph to be taken in relation to that application;

(c)in the case of a reference under paragraph 9 of that Schedule, are required by that paragraph to be taken in relation to that reference,

may be taken concurrently (so far as practicable) with the proceedings required by Schedule 8 to this Act to be taken in relation to the application for consent under section 37 above.

(5)Where, for a purpose connected with the proposed installation of an electric line, a licence holder makes—

(a)an application to the Secretary of State under paragraph 6 of Schedule 4 to this Act for the necessary wayleave; and

(b)a reference to the Secretary of State under paragraph 9 of that Schedule,

the proceedings required by the said paragraph 9 to be taken in relation to the reference under that paragraph may be taken concurrently (so far as practicable) with the proceedings required by the said paragraph 6 to be taken in relation to the application under that paragraph.

Modifications etc. (not altering text)

C4S. 61: transfer of certain functions (S.) (1.7.1999) by S.I. 1999/1750, arts. 1, 2, Sch. 1 (with art. 7)

Marginal Citations