Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
(1)The Authority may by regulations (“tender regulations”) make such provision as appears to it to be appropriate for facilitating the making by a delivery body of—
(a)a decision whether to hold a tender exercise in relation to a relevant electricity project;
(b)in prescribed circumstances, a determination on a competitive basis of any of the matters listed in subsection (2).
(2)Those matters are—
(a)the person by whom a relevant electricity project is to be carried out;
(b)the person to whom a relevant licence is to be granted (whether for the purposes of a relevant electricity project or otherwise);
(c)the person to whom a relevant contract is to be awarded.
(3)The provision mentioned in subsection (1) includes—
(a)provision for the Authority to determine, in prescribed cases, whether a tender exercise should be held, or continued, in relation to a relevant electricity project;
(b)provision for the publication, in prescribed cases, of a proposal for a relevant licence to be granted or for a relevant contract to be awarded;
(c)provision for the inclusion in such a proposal of an invitation to apply for such a licence or to bid for such a contract;
(d)provision restricting applications and bids and imposing requirements as to the period within which they must be made;
(e)provision for regulating the manner in which applications and bids are considered and determined.
(4)The provision mentioned in subsection (1) also includes—
(a)provision conferring functions on a delivery body;
(b)provision authorising the Authority to conduct a review of the exercise by a delivery body of functions conferred on it by the regulations;
(c)provision authorising the Authority to appoint another person to conduct such a review on the Authority’s behalf.
(5)The provision that may be made by virtue of subsection (4)(a) includes provision requiring a delivery body, in prescribed circumstances, to provide information about prescribed matters to the Authority.
(6)Tender regulations—
(a)may make provision by reference to a determination by the Authority or by a delivery body, or to the opinion of the Authority or of a delivery body, as to any matter;
(b)may dispense with or supplement provision made in relation to applications for relevant licences by or under section 6A or 6B.
(7)The approval of the Secretary of State is required for the making of tender regulations.
(8)The making of a determination by virtue of subsection (2)(b) or (c) that a person is to be granted a relevant licence or awarded a relevant contract does not of itself require—
(a)the Authority to exercise its power to grant a relevant licence to the person, or
(b)a contract counterparty to award a relevant contract to the person,
(as the case may be).]
Textual Amendments
F1Ss. 6C-6CD substituted for ss. 6C, 6D (26.10.2023) by Energy Act 2023 (c. 52), s. 334(2)(i), Sch. 15 para. 3
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Part you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Part you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: