Town and Country Planning Act 1990, Cross Heading: Deemed planning permission is up to date with all changes known to be in force on or before 27 December 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)Where the authorisation of a government department is required by virtue of an enactment in respect of development to be carried out by a local authority, or by statutory undertakers who are not a local authority, that department may, on granting that authorisation, direct that planning permission for that development shall be deemed to be granted, subject to such conditions (if any) as may be specified in the direction.
(2)On granting a consent under section 36 or 37 of the M1Electricity Act 1989 in respect of any operation or change of use that constitutes development, the Secretary of State may direct that planning permission for that development and any ancillary development shall be deemed to be granted, subject to such conditions (if any) as may be specified in the direction.
(3)The provisions of this Act (except [F1Part] XII) shall apply in relation to any planning permission deemed to be granted by virtue of a direction under this section as if it had been granted by the Secretary of State on an application referred to him under section 77.
(4)For the purposes of this section development is authorised by a government department if—
(a)any consent, authority or approval to or for the development is granted by the department in pursuance of an enactment;
(b)a compulsory purchase order is confirmed by the department authorising the purchase of land for the purpose of the development;
(c)consent is granted by the department to the appropriation of land for the purpose of the development or the acquisition of land by agreement for that purpose;
(d)authority is given by the department—
(i)for the borrowing of money for the purpose of the development, or
(ii)for the application for that purpose of any money not otherwise so applicable; or
(e)any undertaking is given by the department to pay a grant in respect of the development in accordance with an enactment authorising the payment of such grants;
and references in this section to the authorisation of a government department shall be construed accordingly.
(5)In subsection (2) “ancillary development”, in relation to development consisting of the extension of a generating station, does not include any development which is not directly related to the generation of electricity by that station; and in this subsection “extension” and “generating station” have the same meanings as in Part I of the M2Electricity Act 1989.
Textual Amendments
F1Word in s. 90(3) substituted (25.9.1991) by Planning and Compensation Act 1991 (c. 34, SIF 123:1), s. 31, Sch. 6 para.12 (with s. 84(5)); S.I. 1991/2067, art.3 (subject to art. 4)
Marginal Citations
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: