xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"
Modifications etc. (not altering text)
C1Pt. 3 (ss. 55-106) except ss. 76, 90(2)(5) applied (with modifications) (17.7.1992) by S.I. 1992/1492, regs. 2(1)(b), 3-11
Pt. 3 (ss. 55-106): power to modify conferred (10.11.1993) by 1993 c. 28, s. 171(1)(a); S.I. 1993/2762, art. 3
Pt. 3 (ss. 55-106) applied (5.11.1993) by 1993 c. 42, s. 24(1) (with ss. 2, 30(1), Sch. 2 para.9)
Pt. 3 (ss. 55-106) extended (1.11.1995) by 1995 c. 25, s. 96(2) (with ss. 7(6), 115, 117); S.I. 1995/2765, art. 2
Pt. 3 (ss. 55-106) modified (1.4.1996) by 1994 c. 19, s. 20(3), Sch. 5 Pt. III paras. 15(1), 20 (with ss. 54(5)(7), 55(5), Sch. 17 paras. 22(1), 23(2)); S.I. 1995/3198, art. 4, Sch. 2
Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 9(1)(2)
Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 51
Pt. 3 (ss. 55-106) modified (2.4.2004) by The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), art. 20(1)
Pt. 3 (ss. 55-106) modified (31.10.2005) by The London Thames Gateway Development Corporation (Planning Functions) Order 2005 (S.I. 2005/2721), art. 4
Pt. 3 (ss. 55-106) modified (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), art. 21(1) (with arts. 3(5), 15(3))
Pt. 3 (ss. 55-106) applied (7.6.2006) by Planning and Compulsory Purchase Act 2004 (c. 5), ss. 89, 121, Sch. 4 para. 3(2) (with s. 111); S.I. 2006/1281, art. 2
Pt. 3 (ss. 55-106) modified (22.11.2006) by The Docklands Light Railway (Stratford International Extension) Order 2006 (S.I. 2006/2905), art. 17(1) (with art. 43)
Pt. 3 (ss. 55-106) modified (13.12.2006) by The Luton Dunstable Translink Order 2006 (S.I. 2006/3118), art. 18(1)
C2Pt. 3 (ss. 55-106) modified (4.5.2005) by The Telford Railfreight Terminal (Donnington) Order 2005 (S.I. 2005/1163), art. 25(2) (with art. 30)
Pt. 3 modified (23.8.2007) by The Docklands Light Railway (Capacity Enhancement and 2012 Games Preparation) Order 2007 (S.I. 2007/2297), art. 17(1) (with arts. 3(6), 12(3))
C3Pt. 3 modified (28.9.2007) by The London Gateway Logistics and Commercial Centre Order 2007 (S.I. 2007/2657), art. 27(1) (with art. 19, Sch. 3 para. 13(2))
C4Pt. 3 modified (22.7.2008) by Crossrail Act 2008 (c. 18), s. 10(1)
C5Pt. 3 modified (14.10.2008) by The Felixstowe Branch Line and Ipswich Yard Improvement Order 2008 (S.I. 2008/2512), art. 34(1) (with art. 36(3))
C6Pt. 3 modified (20.7.2010) by The Network Rail (Nuneaton North Chord) Order 2010 (S.I. 2010/1721), art. 28(1)
C7Pt. 3 modified (27.8.2010) by The Llangollen and Corwen Railway Order 2010 (S.I. 2010/2136), art. 11(1)
C8Pt. 3 applied (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), arts. 1, 47(1) (with art. 51, Sch. 10 paras. 68, 85)
C9Pt. 3 modified (21.4.2011) by The Network Rail (Hitchin (Cambridge Junction)) Order 2011 (S.I. 2011/1072), arts. 1, 36(2)
C10Pt. 3 applied (5.4.2017) by The Keuper Underground Gas Storage Facility Order 2017 (S.I. 2017/433), arts. 1, 38(2)
Textual Amendments
F1Ss. 62ZA-62ZD and cross-heading inserted (6.9.2015 for specified purposes, 16.3.2016 in so far as not already in force) by Planning (Wales) Act 2015 (anaw 4), ss. 29(2), 58(2)(b)(4)(b); S.I. 2016/52, art. 5(a) (with art. 9)
(1)This section applies where an application is made to a local planning authority in Wales—
(a)for planning permission, or
(b)for any consent, agreement or approval required by any condition or limitation subject to which planning permission has been granted.
(2)In the case of an application for planning permission, if the authority think the application (or anything accompanying it) does not comply with a validation requirement imposed under section 62, they must give the applicant notice to that effect.
(3)The notice must—
(a)identify the requirement in question, and
(b)set out the authority's reasons for thinking the application does not comply with it.
(4)In the case of an application for a consent, agreement or approval mentioned in subsection (1)(b), the authority must give notice to the applicant if they think that—
(a)the application does not comply with the terms of the planning permission in question, or
(b)a period prescribed under section 74(1)(e) or 78(2) does not begin to run in relation to the application,
by virtue of a failure to include information in the application or to provide documents or other materials with it (whether at all or in a particular manner).
(5)The notice must identify—
(a)the information, documents or materials in question, and
(b)the paragraph of subsection (4) which the authority think applies.
(6)A development order may make provision about the giving of notice under this section (including provision about information to be included in the notice and how and when the notice is to be given).
(7)A requirement imposed under section 62 is a validation requirement in relation to an application for planning permission if the effect of the application failing to comply with the requirement is that—
(a)the local planning authority must not entertain the application (see section 327A), or
(b)the period prescribed under section 78(2) does not begin to run in relation to the application.
(1)If a local planning authority give an applicant notice under section 62ZA, the applicant may appeal to the Welsh Ministers.
(2)In a case relating to an application for planning permission, the appeal may be brought on any one or more of the following grounds—
(a)that the application complies with the requirement identified in the notice given under section 62ZA(2);
(b)that the application is not one to which the requirement applies;
(c)that the requirement is not a validation requirement in relation to the application;
(d)in the case of a requirement imposed under subsection (3) of section 62, that the requirement does not comply with subsection (4A) of that section.
(3)In a case relating to an application for a consent, agreement or approval mentioned in section 62ZA(1)(b), the appeal may be brought on any one or more of the following grounds—
(a)that the application included the information, or was accompanied by the documents or other materials, identified in the notice given under section 62ZA(4);
(b)in a case where notice is given under section 62ZA(4)(a), that the provision of the information, documents or materials is not required in order to comply with the terms of the planning permission;
(c)in a case where notice is given under section 62ZA(4)(b), that the period prescribed under section 74(1)(e) or 78(2) (as the case may be) begins to run in relation to the application irrespective of whether the information, documents or materials are provided.
(4)The appeal must be made by giving notice that complies with any requirements prescribed by a development order.
(5)The requirements may relate to how and when the notice is to be given and the information that is to accompany it.
(6)The appeal is to be determined on the basis of representations in writing.
(7)The Welsh Ministers must either—
(a)dismiss the appeal, or
(b)quash or vary the notice to which it relates.
(8)The Welsh Ministers' decision on the appeal is final.
(1)Unless a direction otherwise is given under section 62ZD(1), an appeal under section 62ZB is to be determined by a person appointed by the Welsh Ministers.
(2)In this section and section 62ZD, “appointed person” means a person appointed under subsection (1).
(3)At any time before an appointed person determines an appeal, the Welsh Ministers may—
(a)revoke the person's appointment, and
(b)appoint another person under subsection (1) to determine the appeal.
(4)An appointed person has the same powers and duties in relation to an appeal as the Welsh Ministers have under sections 62ZB(7) and 322C and under any regulations made under section 323A.
(5)An appointed person's decision on an appeal is to be treated as the decision of the Welsh Ministers.
(6)The validity of an appointed person's decision on an appeal may not be questioned by the appellant or the local planning authority in legal proceedings on the ground that the appeal ought to have been determined by the Welsh Ministers and not by an appointed person, unless the appellant or the authority challenge the appointed person's power to determine the appeal before the person's decision is given.
(1)The Welsh Ministers may direct that an appeal under section 62ZB which would otherwise be determined by an appointed person is instead to be determined by the Welsh Ministers.
(2)The Welsh Ministers must serve a copy of the direction on—
(a)the person (if any) appointed to determine the appeal,
(b)the appellant, and
(c)the local planning authority.
(3)In determining the appeal, the Welsh Ministers may take into account any report made to them by a person previously appointed to determine the appeal.
(4)The Welsh Ministers may by a further direction revoke a direction under subsection (1) at any time before the appeal is determined.
(5)The Welsh Ministers must serve a copy of a direction under subsection (4) on—
(a)the person (if any) previously appointed to determine the appeal,
(b)the appellant, and
(c)the local planning authority.
(6)Where the Welsh Ministers give a direction under subsection (4)—
(a)they must appoint a person (the “new appointee”) under section 62ZC(1) to determine the appeal;
(b)anything done by or on behalf of the Welsh Ministers in connection with the appeal that might have been done by an appointed person is, unless the new appointee directs otherwise, to be treated as having been done by the new appointee;
(c)subject to that, section 62ZC applies to the appeal as if no direction under subsection (1) had been given.]