Textual Amendments
F1Sch. 1A inserted (1.4.1996) by 1994 c. 19, s. 18(7), Sch. 4 (with ss. 54(5)(7), 55(5), Sch. 17 paras. 22(1), 23(2)); S.I. 1995/3198, art. 4, Sch. 2
8(1)Claims for payment of compensation under section 107 (including that section as applied by section 108) and sections 115(1) to (4) and 186 shall, subject to sub-paragraph (3), be made to and paid by the local planning authority who took the action by virtue of which the claim arose or, where that action was taken by the Secretary of State, the local planning authority from whom the appeal was made to him or who referred the matter to him or, in the case of an order made or notice served by him by virtue of section 100, 104 or 185, the appropriate authority, and references in those sections to a local planning authority shall be construed accordingly.E+W
(2) In this paragraph “ appropriate authority ” means—
(a)in the case of a claim for compensation under section 107 or 108, the local planning authority who granted, or are to be treated for the purposes of section 107 as having granted, the planning permission the revocation or modification of which gave rise to the claim; and
(b)in the case of a claim for compensation under section 115(1) to (4) or 186, the local planning authority named in the relevant order or stop notice of the Secretary of State.
[F2(2A)Sub-paragraph (2B) applies where the planning permission the revocation or modification of which gave rise to the claim was granted by the Welsh Ministers by virtue of section 62D, 62F, 62M or 62O.
(2B)The local planning authority to which the application for planning permission would, but for the section in question, have been made, are to be treated for the purposes of sub-paragraph (2)(a) as having granted the permission.]
(3)The Secretary of State may, after consultation with all the authorities concerned, direct that where a local planning authority is liable to pay compensation under any of the provisions mentioned in sub-paragraph (1) in any particular case or class of case they shall be entitled to be reimbursed the whole of the compensation or such proportion of it as he may direct from one or more authorities specified in the direction.
Textual Amendments
F2Sch. 1A para. 8(2A)(2B) inserted (6.9.2015 for specified purposes, 1.3.2016 for specified purposes) by Planning (Wales) Act 2015 (anaw 4), s. 58(2)(b)(4)(b), Sch. 4 para. 22; S.I. 2016/52, art. 3(e)
9E+WClaims for payment of compensation under a tree preservation order by virtue of section 203, and claims for payment of compensation under section 204 by virtue of directions given in pursuance of such an order, shall be made to and paid by the local planning authority who made the order or, in the case of an order made by the Secretary of State, the authority named in the order; and the reference in section 204(2) to the authority exercising functions under the tree preservation order shall have effect subject to the provisions of this paragraph.
10E+WThe local planning authority by whom compensation is to be paid under section 279(1)(a) to statutory undertakers shall be the authority who referred the application for planning permission to the Secretary of State and the appropriate Minister, or from whose decision the appeal was made to them or who served the enforcement notice appealed against, as the case may be.]