Town and Country Planning Act 1990, Cross Heading: Duration of development is up to date with all changes known to be in force on or before 03 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Duration of developmentE+W

1(1)Every planning permission for development [F1E+W

(a)consisting of the winning and working of minerals; or

(b)involving the depositing of mineral waste,]

shall be subject to a condition as to the duration of the development.

(2)Except where a condition is specified under sub-paragraph (3), the condition in the case of planning permission granted or deemed to be granted after 22nd February 1982 is that the [F2winning and working of minerals or the depositing of mineral waste] must cease not later than the expiration of the period of 60 years beginning with the date of the permission.

(3)An authority granting planning permission after that date or directing after that date that planning permission shall be deemed to be granted may specify a longer or shorter period than 60 years, and if they do so, the condition is that the [F2winning and working of minerals or the depositing of mineral waste] must cease not later than the expiration of a period of the specified length beginning with the date of the permission.(4)A longer or shorter period than 60 years may be prescribed for the purposes of sub-paragraphs (2) and (3).

(5)The condition in the case of planning permission granted or deemed to have been granted before 22nd February 1982 is that the [F2winning and working of minerals or the depositing of mineral waste] must cease not later than the expiration of the period of 60 years beginning with that date.

(6)A condition to which planning permission for development [F3consisting of the winning and working of minerals] is subject by virtue of this paragraph—

(a)is not to be regarded for the purposes of the planning Acts as a condition such as is mentioned in section 72(1)(b); but

(b)is to be regarded for the purposes of sections 78 and 79 as a condition imposed by a decision of the local planning authority, and may accordingly be the subject of an appeal under section 78.

Textual Amendments

F1Words in Sch. 5 para. 1(1) substituted (25.9.1991) by Planning and Compensation Act 1991 (c. 34, SIF 123:1), s. 21, Sch. 1 para. 14(1) (with s. 84(5)); S.I. 1991/2067, art.3 (subject to art. 4)

F2Words in Sch. 5 para. 1(2)(3)(5) substituted (25.9.1991) by Planning and Compensation Act 1991 (c. 34, SIF 123:1), s. 21, Sch. 1 para. 14(2)(with s. 84(5)); S.I. 1991/2067, art.3 (subject to art. 4)