Town and Country Planning Act 1990, PART 2 is up to date with all changes known to be in force on or before 20 February 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
Textual Amendments
F1Sch. 7A inserted (3.11.2023 for specified purposes, 12.2.2024 for specified purposes) by Environment Act 2021 (c. 30), s. 147(3), Sch. 14 para. 2 (with s. 144); S.I. 2023/1170, reg. 2(d); S.I. 2024/44, reg. 2(1)(d)(2) (with regs. 3, 4)
Modifications etc. (not altering text)
C1Sch. 7A Pt. 2 applied (with modifications) (12.2.2024) by The Biodiversity Gain Requirements (Irreplaceable Habitat) Regulations 2024 (S.I. 2024/48), regs. 1(1), 3 (with reg. 4)
C2Sch. 7A Pt. 2 applied (with modifications) (12.2.2024) by The Biodiversity Gain (Town and Country Planning) (Modifications and Amendments) (England) Regulations 2024 (S.I. 2024/50), regs. 1(2), 3-8
13(1)Every planning permission granted for the development of land in England shall be deemed to have been granted subject to the condition in sub-paragraph (2).
(2)The condition is that the development may not be begun unless—
(a)a biodiversity gain plan has been submitted to the planning authority (see paragraph 14), and
(b)the planning authority has approved the plan (see paragraph 15).
14(1)For the purposes of paragraph 13(2)(a), a biodiversity gain plan is a plan which—
(a)relates to development for which planning permission is granted, and
(b)specifies the matters referred to in sub-paragraph (2).
(2)The matters are—
(a)information about the steps taken or to be taken to minimise the adverse effect of the development on the biodiversity of the onsite habitat and any other habitat,
(b)the pre-development biodiversity value of the onsite habitat,
(c)the post-development biodiversity value of the onsite habitat,
(d)any registered offsite biodiversity gain allocated to the development and the biodiversity value of that gain in relation to the development,
(e)any biodiversity credits purchased for the development, and
(f)such other matters as the Secretary of State may by regulations specify.
(3)The Secretary of State may by regulations make provision about—
(a)any other matters to be included in a biodiversity gain plan;
(b)the form of a biodiversity gain plan;
(c)the procedure to be followed in relation to the submission of a biodiversity gain plan (including the time by which a plan must be submitted);
(d)persons who may or must submit a biodiversity gain plan.
[F2(4)Section 327ZA applies to the power conferred by sub-paragraph (3) as if a biodiversity gain plan were an “associated document” within the meaning of that section.]
Textual Amendments
F2Sch. 7A para. 14(4) inserted (25.4.2024) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 124(3), 255(3)(b) (with s. 247); S.I. 2024/452, reg. 3(i)
15(1)For the purposes of paragraph 13(2)(b) a planning authority to which a biodiversity gain plan is submitted must approve the plan if, and only if, it is satisfied as to the matters specified in sub-paragraph (2).
(2)The matters are—
(a)that the pre-development biodiversity value of the onsite habitat is as specified in the plan,
(b)that the post-development biodiversity value of the onsite habitat is at least the value specified in the plan,
(c)that, in a case where any registered offsite biodiversity gain is specified in the plan as allocated to the development—
(i)the registered offsite biodiversity gain is so allocated (and, if the allocation is conditional, that any conditions attaching to the allocation have been met or will be met by the time the development begins), and
(ii)the registered offsite biodiversity gain has the biodiversity value specified in the plan in relation to the development,
(d)that any biodiversity credits specified in the plan as purchased for the development have been so purchased,
(e)that the biodiversity gain objective is met, and
(f)any other matters specified in the plan under paragraph 14(2)(f).
16The Secretary of State may make regulations as to—
(a)the procedure which a planning authority is to follow in determining whether to approve a biodiversity gain plan (including the time by which a determination must be made);
(b)factors which may or must be taken into account in making such a determination;
(c)appeals relating to such a determination.
17Paragraph 13 does not apply in relation to—
(a)development for which planning permission is granted—
(i)by a development order, or
(ii)under section 293A (urgent Crown development), or
(b)development of such other description as the Secretary of State may by regulations specify.
18(1)The Secretary of State may by regulations make provision modifying or excluding the application of this Part of this Schedule in relation to any development for which planning permission is granted where the onsite habitat is “irreplaceable habitat” as defined in the regulations.
(2)Regulations under this paragraph must make provision requiring, in relation to any such development, the making of arrangements for the purpose of minimising the adverse effect of the development on the biodiversity of the onsite habitat.
(3)Regulations under this paragraph may confer powers and duties, including powers and duties in relation to the giving of guidance, on Natural England.
19(1)The Secretary of State may by regulations make provision modifying the application of this Part of this Schedule in relation to—
(a)the grant of outline planning permission, where the reservation of matters for subsequent approval has the effect of requiring or permitting development to proceed in phases, or
(b)the grant of any kind of planning permission, where the grant is subject to conditions (whether requiring the subsequent approval of any matters or otherwise) having that effect.
(2)Regulations under this paragraph may include provision for a grant of planning permission referred to in sub-paragraph (1)(a) or (b) to be subject to conditions relating to meeting the biodiversity gain objective referred to in paragraph 2.
20(1)The Secretary of State may by regulations make provision modifying or excluding the application of this Part of this Schedule in relation to development for which—
(a)planning permission is granted under section 73A (planning permission for development already carried out), or
(b)planning permission is granted by an order under section 102 (orders requiring discontinuance of use etc).
(2)Regulations under this paragraph may in particular include provision—
(a)for paragraph 13 not to apply in relation to the grant of planning permission referred to in sub-paragraph (1)(a) or (b);
(b)for the grant of any such planning permission to be subject to other conditions relating to meeting the biodiversity gain objective.
(3)The conditions referred to in sub-paragraph (2)(b) may include conditions requiring—
(a)habitat enhancement on the land to which the planning permission relates;
(b)the allocation of registered offsite biodiversity gain to any development for which the planning permission is granted;
(c)the purchase of biodiversity credits for any such development.
21The Secretary of State may by regulations make provision to apply this Part of this Schedule in relation to development for which planning permission is granted under section 141 or 177(1), with such modifications or exclusions as may be specified in the regulations.]
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: