C3C4C5C6C7C8C9C10C11 Part III Control over development

Annotations:
Modifications etc. (not altering text)
C3

Pt. 3 (ss. 55-106) except ss. 76, 90(2)(5) applied (with modifications) (17.7.1992) by S.I. 1992/1492, regs. 2(1)(b), 3-11

Pt. 3 (ss. 55-106): power to modify conferred (10.11.1993) by 1993 c. 28, s. 171(1)(a); S.I. 1993/2762, art. 3

Pt. 3 (ss. 55-106) applied (5.11.1993) by 1993 c. 42, s. 24(1) (with ss. 2, 30(1), Sch. 2 para.9)

Pt. 3 (ss. 55-106) extended (1.11.1995) by 1995 c. 25, s. 96(2) (with ss. 7(6), 115, 117); S.I. 1995/2765, art. 2

Pt. 3 (ss. 55-106) modified (1.4.1996) by 1994 c. 19, s. 20(3), Sch. 5 Pt. III paras. 15(1), 20 (with ss. 54(5)(7), 55(5), Sch. 17 paras. 22(1), 23(2)); S.I. 1995/3198, art. 4, Sch. 2

Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 9(1)(2)

Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 51

Pt. 3 (ss. 55-106) modified (2.4.2004) by The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), art. 20(1)

Pt. 3 (ss. 55-106) modified (31.10.2005) by The London Thames Gateway Development Corporation (Planning Functions) Order 2005 (S.I. 2005/2721), art. 4

Pt. 3 (ss. 55-106) modified (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), art. 21(1) (with arts. 3(5), 15(3))

Pt. 3 (ss. 55-106) applied (7.6.2006) by Planning and Compulsory Purchase Act 2004 (c. 5), ss. 89, 121, Sch. 4 para. 3(2) (with s. 111); S.I. 2006/1281, art. 2

Pt. 3 (ss. 55-106) modified (22.11.2006) by The Docklands Light Railway (Stratford International Extension) Order 2006 (S.I. 2006/2905), art. 17(1) (with art. 43)

Pt. 3 (ss. 55-106) modified (13.12.2006) by The Luton Dunstable Translink Order 2006 (S.I. 2006/3118), art. 18(1)

C6

Pt. 3 modified (22.7.2008) by Crossrail Act 2008 (c. 18), s. 10(1)

Other controls over development

C1C2C12C13106F1Planning obligations.

C161

Any person interested in land in the area of a local planning authority may, by agreement or otherwise, enter into an obligation (referred to in this section and sections 106A F9to 106C as “ a planning obligation ”), enforceable to the extent mentioned in subsection (3)—

a

restricting the development or use of the land in any specified way;

b

requiring specified operations or activities to be carried out in, on, under or over the land;

c

requiring the land to be used in any specified way; or

d

requiring a sum or sums to be paid to the authority F2(or, in a case where section 2E applies, to the Greater London Authority) on a specified date or dates or periodically.

F31A

In the case of a development consent obligation, the reference to development in subsection (1)(a) includes anything that constitutes development for the purposes of the Planning Act 2008.

2

A planning obligation may—

a

be unconditional or subject to conditions;

b

impose any restriction or requirement mentioned in subsection (1)(a) to (c) either indefinitely or for such period or periods as may be specified; and

c

if it requires a sum or sums to be paid, require the payment of a specified amount or an amount determined in accordance with the instrument by which the obligation is entered into and, if it requires the payment of periodical sums, require them to be paid indefinitely or for a specified period.

C143

Subject to subsection (4) a planning obligation is enforceable by the authority identified in accordance with subsection (9)(d)—

a

against the person entering into the obligation; and

b

against any person deriving title from that person.

4

The instrument by which a planning obligation is entered into may provide that a person shall not be bound by the obligation in respect of any period during which he no longer has an interest in the land.

5

A restriction or requirement imposed under a planning obligation is enforceable by injunction.

6

Without prejudice to subsection (5), if there is a breach of a requirement in a planning obligation to carry out any operations in, on, under or over the land to which the obligation relates, the authority by whom the obligation is enforceable may—

a

enter the land and carry out the operations; and

b

recover from the person or persons against whom the obligation is enforceable any expenses reasonably incurred by them in doing so.

7

Before an authority exercise their power under subsection (6)(a) they shall give not less than twenty-one days’ notice of their intention to do so to any person against whom the planning obligation is enforceable.

8

Any person who wilfully obstructs a person acting in the exercise of a power under subsection (6)(a) shall be guilty of an offence and liable on summary conviction to a fine not exceeding level 3 on the standard scale.

9

A planning obligation may not be entered into except by an instrument executed as a deed which—

a

states that the obligation is a planning obligation for the purposes of this section;

F4aa

if the obligation is a development consent obligation, contains a statement to that effect;

b

identifies the land in which the person entering into the obligation is interested;

c

identifies the person entering into the obligation and states what his interest in the land is; and

C15d

identifies the local planning authority by whom the obligation is enforceable. F5and, in a case where section 2E applies, identifies the Mayor of London as an authority by whom the obligation is also enforceable

10

A copy of any such instrument shall be given to the F6authority so identified F6local planning authority so identified and, in a case where section 2E applies, to the Mayor of London .

11

A planning obligation shall be a local land charge and for the purposes of the M1Local Land Charges Act 1975 the authority by whom the obligation is enforceable shall be treated as the originating authority as respects such a charge.

12

Regulations may provide for the charging on the land of—

a

any sum or sums required to be paid under a planning obligation; and

b

any expenses recoverable by a local planning authority F7or the Mayor of London under subsection (6)(b),

and this section and sections 106A F10to 106BC shall have effect subject to any such regulations.

13

In this section “ specified ” means specified in the instrument by which the planning obligation is entered into and in this section and section 106A “ land ” has the same meaning as in the M2 Local Land Charges Act 1975.

F814

In this section and section 106A “ development consent obligation ” means a planning obligation entered into in connection with an application (or a proposed application) for an order granting development consent.