Print Options
PrintThe Whole
Act
PrintThe Whole
Part
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Section 106B


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Version Superseded: 01/04/2012
Status:
Point in time view as at 01/10/2011. This version of this provision has been superseded.

Status
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Changes to legislation:
Town and Country Planning Act 1990, Section 106B is up to date with all changes known to be in force on or before 09 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
106BAppeals.E+W
(1)Where [an authority]—[ (other than the Secretary of State or the Infrastructure Planning Commission)]
(a)fail to give notice as mentioned in section 106A(7); or
(b)determine that a planning obligation shall continue to have effect without modification,
the applicant may appeal to the Secretary of State.
(2)For the purposes of an appeal under subsection (1)(a), it shall be assumed that the authority have determined that the planning obligation shall continue to have effect without modification.
(3)An appeal under this section shall be made by notice served within such period and in such manner as may be prescribed.
(4)Subsections (6) to (9) of section 106A apply in relation to appeals to the Secretary of State under this section as they apply in relation to applications to authorities under that section.
(5)Before determining the appeal the Secretary of State shall, if either the applicant or the authority so wish, give each of them an opportunity of appearing before and being heard by a person appointed by the Secretary of State for the purpose.
(6)The determination of an appeal by the Secretary of State under this section shall be final.
(7)Schedule 6 applies to appeals under this section.
[(8)In the application of Schedule 6 to an appeal under this section in a case where the authority mentioned in subsection (1) is the Mayor of London, references in that Schedule to the local planning authority are references to the Mayor of London.]