C1C2C3C4C5C6C7C9C10C11C8 Part III Control over development

Annotations:
Modifications etc. (not altering text)
C1

Pt. 3 (ss. 55-106) except ss. 76, 90(2)(5) applied (with modifications) (17.7.1992) by S.I. 1992/1492, regs. 2(1)(b), 3-11

Pt. 3 (ss. 55-106): power to modify conferred (10.11.1993) by 1993 c. 28, s. 171(1)(a); S.I. 1993/2762, art. 3

Pt. 3 (ss. 55-106) applied (5.11.1993) by 1993 c. 42, s. 24(1) (with ss. 2, 30(1), Sch. 2 para.9)

Pt. 3 (ss. 55-106) extended (1.11.1995) by 1995 c. 25, s. 96(2) (with ss. 7(6), 115, 117); S.I. 1995/2765, art. 2

Pt. 3 (ss. 55-106) modified (1.4.1996) by 1994 c. 19, s. 20(3), Sch. 5 Pt. III paras. 15(1), 20 (with ss. 54(5)(7), 55(5), Sch. 17 paras. 22(1), 23(2)); S.I. 1995/3198, art. 4, Sch. 2

Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 9(1)(2)

Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 51

Pt. 3 (ss. 55-106) modified (2.4.2004) by The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), art. 20(1)

Pt. 3 (ss. 55-106) modified (31.10.2005) by The London Thames Gateway Development Corporation (Planning Functions) Order 2005 (S.I. 2005/2721), art. 4

Pt. 3 (ss. 55-106) modified (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), art. 21(1) (with arts. 3(5), 15(3))

Pt. 3 (ss. 55-106) applied (7.6.2006) by Planning and Compulsory Purchase Act 2004 (c. 5), ss. 89, 121, Sch. 4 para. 3(2) (with s. 111); S.I. 2006/1281, art. 2

Pt. 3 (ss. 55-106) modified (22.11.2006) by The Docklands Light Railway (Stratford International Extension) Order 2006 (S.I. 2006/2905), art. 17(1) (with art. 43)

Pt. 3 (ss. 55-106) modified (13.12.2006) by The Luton Dunstable Translink Order 2006 (S.I. 2006/3118), art. 18(1)

C4

Pt. 3 modified (22.7.2008) by Crossrail Act 2008 (c. 18), s. 10(1)

Other controls over development

106CLegal challenges relating to development consent obligations

1

A court may entertain proceedings for questioning a failure by the Secretary of State F10... to give notice as mentioned in section 106A(7) F5or 106BA(9) only if—

a

the proceedings are brought by a claim for judicial review, and

b

the claim form is filed F12before the end of the period of 6 weeks beginning with F6the day after the day on which the period prescribed under section 106A(7) F5or 106BA(9) ends.

F31A

If no period is prescribed under section 106BA(9), the period of 6 weeks referred to in subsection (1)(b) that applies in relation to proceedings for failure to give notice as mentioned in subsection (9) of section 106BA begins with F1the day after the expiry of the period mentioned in that subsection that applies in the applicant's case.

2

A court may entertain proceedings for questioning a determination by the Secretary of State F10... that a planning obligation shall continue to have effect without modification only if—

a

the proceedings are brought by a claim for judicial review, and

b

the claim form is filed F8before the end of the period of 6 weeks beginning with F4the day after the day on which notice of the determination is given under section 106A(7) F2or 106BA(9).

F113

A court may entertain proceedings for questioning a determination by the Secretary of State on an application under section 106BA that a planning obligation shall be modified otherwise than in accordance with the application only if—

a

the proceedings are brought by a claim for judicial review, and

b

the claim form is filed F7before the end of the period of 6 weeks beginning with F9the day after the day on which notice of the determination is given under section 106BA(9).