Print Options
PrintThe Whole
Act
PrintThe Whole
Part
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Section 192


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 25/11/1991.
Changes to legislation:
Town and Country Planning Act 1990, Section 192 is up to date with all changes known to be in force on or before 06 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
[192 Certificate of lawfulness of proposed use or development.E+W
(1)If any person wishes to ascertain whether—
(a)any proposed use of buildings or other land; or
(b)any operations proposed to be carried out in, on, over or under land,
would be lawful, he may make an application for the purpose to the local planning authority specifying the land and describing the use or operations in question.
(2)If, on an application under this section, the local planning authority are provided with information satisfying them that the use or operations described in the application would be lawful if instituted or begun at the time of the application, they shall issue a certificate to that effect; and in any other case they shall refuse the application.
(3)A certificate under this section shall—
(a)specify the land to which it relates;
(b)describe the use or operations in question (in the case of any use falling within one of the classes specified in an order under section 55(2)(f), identifying it by reference to that class);
(c)give the reasons for determining the use or operations to be lawful; and
(d)specify the date of the application for the certificate.
(4)The lawfulness of any use or operations for which a certificate is in force under this section shall be conclusively presumed unless there is a material change, before the use is instituted or the operations are begun, in any of the matters relevant to determining such lawfulness.]