- Latest available (Revised)
- Point in Time (02/12/2021)
- Original (As enacted)
Point in time view as at 02/12/2021. This version of this provision has been superseded.
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Town and Country Planning Act 1990, Section 57 is up to date with all changes known to be in force on or before 18 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)Subject to the following provisions of this section, planning permission is required for the carrying out of any development of land.
[F1(1A)Subsection (1) is subject to section 33(1) of the Planning Act 2008 (exclusion of requirement for planning permission etc. for development for which development consent required).]
(2)Where planning permission to develop land has been granted for a limited period, planning permission is not required for the resumption, at the end of that period, of its use for the purpose for which it was normally used before the permission was granted.
(3)Where by a development order [F2, a local development order or a neighbourhood development order] planning permission to develop land has been granted subject to limitations, planning permission is not required for the use of that land which (apart from its use in accordance with that permission) is its normal use.
(4)Where an enforcement notice has been issued in respect of any development of land, planning permission is not required for its use for the purpose for which (in accordance with the provisions of this Part of this Act) it could lawfully have been used if that development had not been carried out.
(5)In determining for the purposes of subsections (2) and (3) what is or was the normal use of land, no account shall be taken of any use begun in contravention of this Part or of previous planning control.
(6)For the purposes of this section a use of land shall be taken to have been begun in contravention of previous planning control if it was begun in contravention of Part III of the 1947 Act, Part III of the 1962 Act or Part III of the 1971 Act.
(7)Subsection (1) has effect subject to Schedule 4 (which makes special provision about use of land on 1st July 1948).
Textual Amendments
F1S. 57(1A) inserted (1.3.2010) by Planning Act 2008 (c. 29), ss. 36, 241, Sch. 2 para. 35 (with s. 226); S.I. 2010/101, art. 2 (with art. 6)
F2Words in s. 57(3) substituted (15.11.2011 for specified purposes, 15.1.2012 for specified purposes, 6.4.2012 for specified purposes, 3.8.2012 for specified purposes) by Localism Act 2011 (c. 20), s. 240(5)(j), Sch. 12 para. 3; S.I. 2012/57, art. 4(1)(h) (with arts. 6, 7, 9-11); S.I. 2012/628, art. 8(a) (with arts. 9, 12, 13, 16, 18-20) (as amended (3.8.2012) by S.I. 2012/2029, arts. 2, 4); S.I. 2012/2029, arts. 2, 3(a) (with art. 5) (as amended (6.4.2013) by S.I. 2013/797, art. 4)
Modifications etc. (not altering text)
C1S. 57(2) applied (with modifications) (9.4.2013) by The Hinkley Point C (Nuclear Generating Station) Order 2013 (S.I. 2013/648), arts. 1, 10(2) (with arts. 48, 68, 79)
C2S. 57(2) applied (with modifications) (9.2.2016) by The National Grid (Hinkley Point C Connection Project) Order 2016 (S.I. 2016/49), arts. 1, 8 (with art. 32)
C3S. 57(2) applied (24.8.2017) by The National Grid (Richborough Connection Project) Development Consent Order 2017 (S.I. 2017/817), arts. 1, 8(2) (with art. 22)
C4S. 57(2) applied (with modifications) (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 9(1) (with art. 37)
C5S. 57(2) excluded (11.2.2021) by High Speed Rail (West Midlands - Crewe) Act 2021 (c. 2), ss. 58(4), 64(1)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: