- Latest available (Revised)
- Point in Time (09/06/2015)
- Original (As enacted)
Version Superseded: 12/05/2016
Point in time view as at 09/06/2015. This version of this provision has been superseded.
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Town and Country Planning Act 1990, Section 60 is up to date with all changes known to be in force on or before 12 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)Planning permission granted by a development order may be granted either unconditionally or subject to such conditions or limitations as may be specified in the order.
(2)Without prejudice to the generality of subsection (1), where planning permission is granted by a development order for the erection, extension or alteration of any buildings, the order may require the approval of the local planning authority to be obtained with respect to the design or external appearance of the buildings.
[F1(2A)Without prejudice to the generality of subsection (1), where planning permission is granted by a development order for development consisting of a change in the use of land in England, the order may require the approval of the local planning authority, or of the Secretary of State, to be obtained—
(a)for the use of the land for the new use;
(b)with respect to matters that relate to the new use and are specified in the order.
(2B)Without prejudice to the generality of subsection (1), a development order may include provision for ensuring—
(a)that, before a person in reliance on planning permission granted by the order carries out development of land in England that is a dwelling house or is within the curtilage of a dwelling house—
(i)a written description, and a plan, of the proposed development are given to the local planning authority,
(ii)notice of the proposed development, and of the period during which representations about it may be made to the local planning authority, is served by the local planning authority on the owner or occupier of any adjoining premises, and
(iii)that period has ended, and
(b)that, where within that period an owner or occupier of any adjoining premises objects to the proposed development, it may be carried out in reliance on the permission only if the local planning authority consider that it would not have an unacceptable impact on the amenity of adjoining premises.
(2C)In subsection (2B) “adjoining premises” includes any land adjoining—
(a)the dwelling house concerned, or
(b)the boundary of its curtilage.]
(3)Without prejudice to the generality of subsection (1), where planning permission is granted by a development order for development of a specified class, the order may enable the Secretary of State or the local planning authority to direct that the permission shall not apply either—
(a)in relation to development in a particular area, or
(b)in relation to any particular development.
(4)Any provision of a development order by which permission is granted for the use of land for any purpose on a limited number of days in a period specified in that provision shall (without prejudice to the generality of references in this Act to limitations) be taken to be a provision granting permission for the use of land for any purpose subject to the limitation that the land shall not be used for any one purpose in pursuance of that provision on more than that number of days in that period.
Subordinate Legislation Made
P1S. 60 power previously exercised by S.I. 1990/2032
P2S. 60(1): s. 59 (with ss. 60(1), 61(1) and 333(7)) power exercised by S.I. 1991/1536
Textual Amendments
F1S. 60(2A)-(2C) inserted (25.4.2013) by Growth and Infrastructure Act 2013 (c. 27), ss. 4(1), 35(2)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: