Print Options
PrintThe Whole
Act
PrintThe Whole
Part
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Section 61D


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Version Superseded: 12/02/2015
Status:
Point in time view as at 30/04/2012. This version of this provision has been superseded.

Status
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Changes to legislation:
Town and Country Planning Act 1990, Section 61D is up to date with all changes known to be in force on or before 06 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
[61DEffect of revision or revocation of development order on incomplete developmentE+W
(1)A development order or local development order may include provision permitting the completion of development if —
(a)planning permission is granted by the order in respect of the development, and
(b)the planning permission is withdrawn at a time after the development is started but before it is completed.
(2)Planning permission granted by a development order is withdrawn—
(a)if the order is revoked;
(b)if the order is amended so that it ceases to grant planning permission in respect of the development or materially changes any condition or limitation to which the grant of permission is subject;
(c)by the issue of a direction under powers conferred by the order.
(3)Planning permission granted by a local development order is withdrawn—
(a)if the order is revoked under section 61A(6) or 61B(8);
(b)if the order is revised in pursuance of paragraph 2 of Schedule 4A so that it ceases to grant planning permission in respect of the development or materially changes any condition or limitation to which the grant of permission is subject;
(c)by the issue of a direction under powers conferred by the order.
(4)The power under this section to include provision in a development order or a local development order may be exercised differently for different purposes.]