Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)A local planning authority in England may decline to determine an application for planning permission for the development of any land if—
(a)the development is development of a prescribed description,
(b)the application is made by—
(i)a person who has previously made an application for planning permission for development of land all or any part of which is in the local planning authority’s area at the time the current application is made (“the earlier application”), or
(ii)a person who has a connection of a prescribed description with the development to which the earlier application related (“the earlier development”),
(c)the earlier development was of a description prescribed under paragraph (a), and
(d)subsection (2) or (3) applies to the earlier development.
(2)This subsection applies to the earlier development if the earlier development has not begun.
(3)This subsection applies to the earlier development if—
(a)the earlier development has begun but has not been substantially completed, and
(b)the local planning authority is of the opinion that the carrying out of the earlier development has been unreasonably slow.
(4)In forming an opinion as to whether the carrying out of the earlier development has been unreasonably slow, the local planning authority must have regard to all the circumstances, including in particular—
(a)in a case where a commencement notice under section 93G has been given, whether the development—
(i)was begun by the date specified in the notice, and
(ii)was carried out in accordance with any timescales specified in it,
(b)whether a completion notice was served in respect of the earlier development under section 93H or (before the coming into force of section 93H) section 94 or 96 and, if so, whether the permission granted became invalid under section 93J or (as the case may be) section 95, and
(c)any prescribed circumstances.
(5)Where a person applies to a local planning authority for planning permission for development of a description prescribed under subsection (1)(a), the authority may by notice require the person to provide such information, being information of a prescribed description, as the authority may specify in the notice for the purpose of its functions under this section.
(6)If a person does not comply with a notice under subsection (5) within the period of 21 days beginning with the day on which the notice was served, the local planning authority may decline to determine the application.
(7)If a person to whom a notice under subsection (5) is given—
(a)makes a statement purporting to comply with the notice which the person knows to be false or misleading in a material particular, or
(b)recklessly makes such a statement which is false or misleading in a material particular,
the person is guilty of an offence.
(8)A person guilty of an offence under subsection (7) is liable on summary conviction to a fine.
(9)Subsection (1) does not permit a local planning authority to decline to determine an application for planning permission to which section 73, 73A or 73B applies.]
Textual Amendments
F1S. 70D inserted (26.12.2023 for specified purposes) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 113(2), 255(3) (with s. 247)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: