Town and Country Planning Act 1990

73 Determination of applications to develop land without compliance with conditions previously attached.E+W

(1)This section applies, subject to subsection (4), to applications for planning permission for the development of land without complying with conditions subject to which a previous planning permission was granted.

(2)On such an application the local planning authority shall consider only the question of the conditions subject to which planning permission should be granted, and—

(a)if they decide that planning permission should be granted subject to conditions differing from those subject to which the previous permission was granted, or that it should be granted unconditionally, they shall grant planning permission accordingly, and

(b)if they decide that planning permission should be granted subject to the same conditions as those subject to which the previous permission was granted, they shall refuse the application.

(3)[F1Special provision may be made with respect to such applications—

(a)by regulations under section 62 as regards the form and content of the application, and

(b)by a development order as regards the procedure to be followed in connection with the application.]

(4)This section does not apply if the previous planning permission was granted subject to a condition as to the time within which the development to which it related was to be begun and that time has expired without the development having been begun.

[F2(5)Planning permission must not be granted under this section to the extent that it has effect to change a condition subject to which a previous planning permission was granted by extending the time within which—

(a)a development must be started;

(b)an application for approval of reserved matters (within the meaning of section 92) must be made.]

Textual Amendments

F1S. 73(3) repealed (6.8.2004 for certain purposes and otherwise prosp.) by Planning and Compulsory Purchase Act 2004 (c. 5), ss. 42(2), 120, 121, Sch. 9 (with s. 111); S.I. 2004/2097, art. 2

F2S. 73(5) inserted (24.8.2005 for E and otherwise prosp.) by Planning and Compulsory Purchase Act 2004 (c. 5), ss. 51(3), 121 (with s. 111); S.I. 2005/2081, art. 2 (subject to savings in art. 4)

Modifications etc. (not altering text)

C1S. 73: functions of local authority not to be responsibility, of an executive of the authority (E.)(16.11.2000) by virtue of S.I. 2000/2853, reg. 2(1), Sch. 1 para. A. 2

C2S. 73: functions of local authority not to be responsibility of an executive of the authority (E.)(16.11.2000) by virtue of S.I. 2000/2853, reg. 2(1), Sch. 1