xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"
Modifications etc. (not altering text)
C1Pt. 3 (ss. 55-106) except ss. 76, 90(2)(5) applied (with modifications) (17.7.1992) by S.I. 1992/1492, regs. 2(1)(b), 3-11
Pt. 3 (ss. 55-106): power to modify conferred (10.11.1993) by 1993 c. 28, s. 171(1)(a); S.I. 1993/2762, art. 3
Pt. 3 (ss. 55-106) applied (5.11.1993) by 1993 c. 42, s. 24(1) (with ss. 2, 30(1), Sch. 2 para.9)
Pt. 3 (ss. 55-106) extended (1.11.1995) by 1995 c. 25, s. 96(2) (with ss. 7(6), 115, 117); S.I. 1995/2765, art. 2
Pt. 3 (ss. 55-106) modified (1.4.1996) by 1994 c. 19, s. 20(3), Sch. 5 Pt. III paras. 15(1), 20 (with ss. 54(5)(7), 55(5), Sch. 17 paras. 22(1), 23(2)); S.I. 1995/3198, art. 4, Sch. 2
Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 9(1)(2)
Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 51
Pt. 3 (ss. 55-106) modified (2.4.2004) by The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), art. 20(1)
Pt. 3 (ss. 55-106) modified (31.10.2005) by The London Thames Gateway Development Corporation (Planning Functions) Order 2005 (S.I. 2005/2721), art. 4
Pt. 3 (ss. 55-106) modified (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), art. 21(1) (with arts. 3(5), 15(3))
Pt. 3 (ss. 55-106) applied (7.6.2006) by Planning and Compulsory Purchase Act 2004 (c. 5), ss. 89, 121, Sch. 4 para. 3(2) (with s. 111); S.I. 2006/1281, art. 2
Pt. 3 (ss. 55-106) modified (22.11.2006) by The Docklands Light Railway (Stratford International Extension) Order 2006 (S.I. 2006/2905), art. 17(1) (with art. 43)
Pt. 3 (ss. 55-106) modified (13.12.2006) by The Luton Dunstable Translink Order 2006 (S.I. 2006/3118), art. 18(1)
C2Pt. 3 (ss. 55-106) modified (4.5.2005) by The Telford Railfreight Terminal (Donnington) Order 2005 (S.I. 2005/1163), art. 25(2) (with art. 30)
Pt. 3 modified (23.8.2007) by The Docklands Light Railway (Capacity Enhancement and 2012 Games Preparation) Order 2007 (S.I. 2007/2297), art. 17(1) (with arts. 3(6), 12(3))
C3Pt. 3 modified (28.9.2007) by The London Gateway Logistics and Commercial Centre Order 2007 (S.I. 2007/2657), art. 27(1) (with art. 19, Sch. 3 para. 13(2))
C4Pt. 3 modified (22.7.2008) by Crossrail Act 2008 (c. 18), s. 10(1)
C5Pt. 3 modified (14.10.2008) by The Felixstowe Branch Line and Ipswich Yard Improvement Order 2008 (S.I. 2008/2512), art. 34(1) (with art. 36(3))
C6Pt. 3 modified (20.7.2010) by The Network Rail (Nuneaton North Chord) Order 2010 (S.I. 2010/1721), art. 28(1)
C7Pt. 3 modified (27.8.2010) by The Llangollen and Corwen Railway Order 2010 (S.I. 2010/2136), art. 11(1)
C8Pt. 3 applied (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), arts. 1, 47(1) (with art. 51, Sch. 10 paras. 68, 85)
C9Pt. 3 modified (21.4.2011) by The Network Rail (Hitchin (Cambridge Junction)) Order 2011 (S.I. 2011/1072), arts. 1, 36(2)
(1)Where a local planning authority—
(a)refuse an application for planning permission or grant it subject to conditions;
(b)refuse an application for any consent, agreement or approval of that authority required by a condition imposed on a grant of planning permission or grant it subject to conditions; or
(c)refuse an application for any approval of that authority required under a development order [F1, a local development order or a neighbourhood development order] or grant it subject to conditions,
the applicant may by notice appeal to the Secretary of State.
(2)A person who has made such an application [F2to the local planning authority] may also appeal to the Secretary of State if the local planning authority have [F3done none of the following]—
(a)given notice to the applicant of their decision on the application;
[F4(aa)given notice to the applicant that they have exercised their power under section 70A [F5or 70B] [F6or 70C] to decline to determine the application;]
(b)given notice to him that the application has been referred to the Secretary of State in accordance with directions given under section 77,
within such period as may be prescribed by the development order or within such extended period as may at any time be agreed upon in writing between the applicant and the authority.
(3)Any appeal under this section shall be made by notice served within such time and in such manner as may be prescribed by a development order.
(4)The time prescribed for the service of such a notice must not be less than—
(a)28 days from the date of notification of the decision; or
(b)in the case of an appeal under subsection (2), 28 days from the end of the period prescribed as mentioned in subsection (2) or, as the case may be, the extended period mentioned in that subsection.
[F7(4A)A notice of appeal under this section must be accompanied by such information as may be prescribed by a development order.
(4B)The power to make a development order under subsection (4A) is exercisable by—
(a)the Secretary of State, in relation to England;
(b)the Welsh Ministers, in relation to Wales.
(4C)Section 333(5) does not apply in relation to a development order under subsection (4A) made by the Welsh Ministers.
(4D)A development order under subsection (4A) made by the Welsh Ministers is subject to annulment in pursuance of a resolution of the National Assembly for Wales.]
(5)For the purposes of the application of sections [F879(1) and (3)], 253(2)(c), 266(1)(b) [F9, 288(10)(b) and 319A(7)(b)] in relation to an appeal under subsection (2), it shall be assumed that the authority decided to refuse the application in question.
Textual Amendments
F1Words in s. 78(1)(c) substituted (15.11.2011 for specified purposes, 15.1.2012 for specified purposes, 6.4.2012 for specified purposes, 3.8.2012 for specified purposes, 6.4.2013 in so far as not already in force) by Localism Act 2011 (c. 20), s. 240(5)(j), Sch. 12 para. 11; S.I. 2012/57, art. 4(1)(h) (with arts. 6, 7, 9-11); S.I. 2012/628, art. 8(a) (with arts. 9, 12, 13, 16, 18-20) (as amended (3.8.2012) by S.I. 2012/2029, arts. 2, 4); S.I. 2012/2029, arts. 2, 3(a) (with art. 5) (as amended (6.4.2013) by S.I. 2013/797, art. 4); S.I. 2013/797, arts. 1(2), 2
F2Words in s. 78(2) inserted (9.5.2013 for E. for specified purposes, 1.10.2013 for specified purposes, 1.10.2014 in so far as not already in force) by Growth and Infrastructure Act 2013 (c. 27), s. 35(1), Sch. 1 para. 8; S.I. 2013/1124, art. 2; S.I. 2013/2143, art. 2(1)(a); S.I. 2014/1531, art. 2
F3Words in s. 78(2) substituted (25.9.1991) by Planning and Compensation Act 1991 (c. 34, SIF 123:1), s. 17(2) (with s. 84(5)); S.I. 1991/2067, art.3 (subject to art. 4)
F4S. 78(2)(aa) substituted (25.9.1991) for 'nor' by Planning and Compensation Act 1991 (c. 34, SIF 123:1), s. 17(2) (with s. 84(5)); S.I. 1991/2067, art. 3 (subject to art. 4)
F5Words in s. 78(2)(aa) inserted (6.4.2009 for E. and otherwise prosp.) by Planning and Compulsory Purchase Act 2004 (c. 5), ss. 43(2), 121 (with s. 111); S.I. 2009/384, art. 2
F6Words in s. 78(2)(aa) inserted (6.4.2012) by Localism Act 2011 (c. 20), ss. 123(3), 240(2) (with s. 144); S.I. 2012/628, art. 8(b) (with arts. 9, 12, 13, 16, 18-20) (as amended (3.8.2012) by S.I. 2012/2029, arts. 2, 4)
F7S. 78(4A)-(4D) inserted (6.4.2009 for E., 30.4.2012 for W.) by Planning Act 2008 (c. 29), s. 241(3)(4), Sch. 11 para. 2 (with s. 226); S.I. 2009/400, art. 5(d); S.I. 2012/802, art. 2(b)
F8Words in s. 78(5) substituted (6.4.2009 for certain purposes and otherwise prosp.) by Planning Act 2008 (c. 29), ss. 196, 241, Sch. 10 para. 3(a) (with s. 226); S.I. 2009/400, art. 3
F9Words in s. 78(5) substituted (6.4.2009 for certain purposes and otherwise prosp.) by Planning Act 2008 (c. 29), ss. 196, 241, Sch. 10 para. 3(b) (with s. 226); S.I. 2009/400, art. 3
Modifications etc. (not altering text)
C10S. 78 modified by S.I. 1989/670, reg. 15 as amended by S.I. 1990/1562, regs. 2, 3, 6
S. 78 applied (with modifications) (6.4.1992) by S.I. 1992/666, reg. 15(1)(3), Sch. 4 Pts. I, IV, V
S. 78 applied (with modifications) (2.8.1999) by S.I. 1999/1892, reg. 2(1), Sch. art. 7, Sch. 2 Pt. I
S. 78 applied (with modifications) (2.8.1999) by S.I. 1999/1892, reg. 2(1), Sch. art. 7, Sch. 2 Pt. II
C11S. 78 restricted (18.12.1996) by 1996 c. 61, s. 9(5), Sch. 6 Pt. IV para. 33
C12S. 78 applied (7.6.2006) by Planning and Compulsory Purchase Act 2004 (c. 5), ss. 89, 121, Sch. 4 para. 5(3) (with s. 111); S.I. 2006/1281, art. 2
C13Ss. 78, 79 applied (with modifications) (6.4.2007) by The Town and Country Planning (Control of Advertisements) (England) Regulations 2007 (S.I. 2007/783), reg. 17, Sch. 4 (as amended (1.10.2013) by S.I. 2013/2114, regs. 1(1), 3)
C14S. 78 restricted (22.7.2008) by Crossrail Act 2008 (c. 18), ss. 10, Sch. 7 para. 31
C15S. 78 applied (22.7.2008) by Crossrail Act 2008 (c. 18), ss. 49, Sch. 16 para. 2(7)
C16S. 78 applied (26.9.2012) by The Network Rail (Ipswich Chord) Order 2012 (S.I. 2012/2284), arts. 1, 35(a) (with art. 26(2))
C17S. 78 applied (in part) (6.11.2012) by The Network Rail (North Doncaster Chord) Order 2012 (S.I. 2012/2635), arts. 1, 7(1)(a) (with art. 35(2))
C18S. 78 applied (with modifications) (28.2.2013) by The Rookery South (Resource Recovery Facility) Order 2011 2013 (S.I. 2013/680), art. 4(1)(a)
C19S. 78 applied (13.3.2013) by The Brechfa Forest West Wind Farm Order 2013 (S.I. 2013/586), arts. 1, 4(1)
C20Ss. 78, 79 applied (15.6.2013) by The Galloper Wind Farm Order 2013 (S.I. 2013/1203), arts. 1, 6(1) (with arts. 11, 12)
C21Ss. 78, 79 applied (31.7.2013) by The East Northamptonshire Resource Management Facility Order 2013 (S.I. 2013/1752), arts. 1, 5(1)(a)
C22Ss. 78, 79 applied (15.8.2013) by The North Blyth Biomass Power Station Order 2013 (S.I. 2013/1873), arts. 1, 4(a) (with art. 30)