Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)This section applies where relevant planning permission is granted for relevant residential development in England.
(2)The relevant planning permission must be granted subject to a condition that a development progress report must be provided to the local planning authority in whose area the development is to be carried out for each reporting period.
(3)The first reporting period in relation to the development is to be a period—
(a)beginning at a prescribed time or by reference to a prescribed event, and
(b)during which the development is begun.
(4)A new reporting period is to begin immediately after the end of a reporting period which is not the last reporting period.
(5)A reporting period which is not the last reporting period is to be a period of 12 months.
(6)The last reporting period is to be a period ending with the day on which the development is completed (subject to any provision made under subsection (9)).
(7)A “development progress report”, in relation to relevant residential development, means a report which sets out—
(a)the progress that has been made, and that remains to be made, towards completing the dwellings the creation of which the development is to involve, as at the end of the reporting period to which the report relates,
(b)the progress which is predicted to be made towards completing those dwellings over each subsequent reporting period up to and including the last reporting period, and
(c)such other information as may be prescribed in regulations under subsection (9).
(8)If relevant planning permission is granted without the condition required by subsection (2), it is to be treated as having been granted subject to that condition.
(9)The Secretary of State may by regulations make provision—
(a)about the form and content of development progress reports;
(b)about when and how development progress reports are to be provided to local planning authorities;
(c)about who may or must provide development progress reports to local planning authorities;
(d)about the provision of development progress reports and other information to local planning authorities where there is a change in circumstances in connection with relevant residential development, such as (for example) where the development is no longer intended to be completed in accordance with—
(i)the relevant planning permission;
(ii)a previous development progress report;
(iii)any timescales specified in a commencement notice given under section 93G;
(e)about when a condition under subsection (2) is to be treated as being discharged;
(f)about when relevant residential development is to be treated as being completed for the purposes of this section.
(10)In this section—
“relevant planning permission” means planning permission other than—
planning permission granted by a development order;
planning permission granted for development carried out before the grant of that permission;
planning permission granted for a limited period;
planning permission granted by an enterprise zone scheme;
planning permission granted by a simplified planning zone scheme;
“relevant residential development” means development which—
involves the creation of one or more dwellings, and
is of a prescribed description.]
Textual Amendments
F1S. 90B and cross-heading inserted (26.12.2023 for specified purposes) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 114(3), 255(3) (with s. 247)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: