Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)This section applies where—
(a)a planning permission relating to land in England is by virtue of section 91 or 92 subject to a condition that the development to which the permission relates must begin before the expiration of a particular period, and development has been begun within that period but has not been completed,
(b)development has begun in accordance with a simplified planning zone scheme in England but has not been completed by the time the area ceases to be a simplified planning zone,
(c)development has begun in accordance with planning permission under an enterprise zone scheme in England but has not been completed by the time the area ceases to be an enterprise zone,
(d)a planning permission under a neighbourhood development order is subject to a condition that the development to which the permission relates must begin before the expiration of a particular period, and development has begun within that period but has not been completed, or
(e)a planning permission under a street vote development order is subject to a condition that the development to which the permission relates must begin before the expiration of a particular period, and development has begun within that period but has not been completed.
(2)If the local planning authority are of the opinion that the development will not be completed within a reasonable period, they may serve a notice (a “completion notice”) stating that the planning permission will cease to have effect at a specified time (the “completion notice deadline”).
(3)The completion notice deadline must be—
(a)at least 12 months after the completion notice was served, and
(b)if the notice was served in a case within subsection (1)(a) or (d) before the end of the period referred to in that provision, at least 12 months after the end of that period.
(4)A completion notice must include—
(a)prescribed information in relation to the right of appeal against the notice, and
(b)any other prescribed information.
(5)A completion notice must be served on—
(a)the owner of the land,
(b)if different, the occupier of the land, and
(c)a person not falling within paragraph (a) or (b) with an interest in the land, being an interest which, in the opinion of the local planning authority, is materially affected by the notice.
(6)The local planning authority may withdraw a completion notice at any time before the completion notice deadline.
(7)If they do so they must immediately give notice of the withdrawal to every person who was served with the completion notice.
(8)If it appears to the Secretary of State to be expedient that a completion notice should be served in respect of any land in England, the Secretary of State may, after consulting the local planning authority, serve such a notice.]
Textual Amendments
F1Ss. 93H-93J and cross-heading inserted (26.12.2023 for specified purposes) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 112(2), 255(3) (with ss. 112(4)(5), 247)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: