Print Options
PrintThe Whole
Act
PrintThe Whole
Part
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Section 95


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 26/12/2023.
Changes to legislation:
Town and Country Planning Act 1990, Section 95 is up to date with all changes known to be in force on or before 09 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
95 Effect of completion notice [in Wales].E+W
(1)A completion notice [served in respect of land in Wales] shall not take effect unless and until it is confirmed by the Secretary of State.
(2)In confirming a completion notice the Secretary of State may substitute some longer period for that specified in the notice as the period at the expiration of which the planning permission is to cease to have effect.
(3)If, within such period as may be specified in a completion notice (which must not be less than 28 days from its service) any person on whom the notice is served so requires, the Secretary of State, before confirming the notice, shall give him and the local planning authority an opportunity of appearing before and being heard by a person appointed by the Secretary of State for the purpose.
(4)If a completion notice takes effect, the planning permission referred to in it shall become invalid at the expiration of the period specified in the notice (whether the original period specified under section 94(2) or a longer period substituted by the Secretary of State under subsection (2)).
(5)Subsection (4) shall not affect any permission so far as development carried out under it before the end of the period mentioned in that subsection is concerned.