Modifications etc. (not altering text)
C1Pt. 3 (ss. 55-106) except ss. 76, 90(2)(5) applied (with modifications) (17.7.1992) by S.I. 1992/1492, regs. 2(1)(b), 3-11
Pt. 3 (ss. 55-106): power to modify conferred (10.11.1993) by 1993 c. 28, s. 171(1)(a); S.I. 1993/2762, art. 3
Pt. 3 (ss. 55-106) applied (5.11.1993) by 1993 c. 42, s. 24(1) (with ss. 2, 30(1), Sch. 2 para.9)
Pt. 3 (ss. 55-106) extended (1.11.1995) by 1995 c. 25, s. 96(2) (with ss. 7(6), 115, 117); S.I. 1995/2765, art. 2
Pt. 3 (ss. 55-106) modified (1.4.1996) by 1994 c. 19, s. 20(3), Sch. 5 Pt. III paras. 15(1), 20 (with ss. 54(5)(7), 55(5), Sch. 17 paras. 22(1), 23(2)); S.I. 1995/3198, art. 4, Sch. 2
Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 9(1)(2)
Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 51
Pt. 3 (ss. 55-106) modified (2.4.2004) by The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), art. 20(1)
Pt. 3 (ss. 55-106) modified (31.10.2005) by The London Thames Gateway Development Corporation (Planning Functions) Order 2005 (S.I. 2005/2721), art. 4
Pt. 3 (ss. 55-106) modified (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), art. 21(1) (with arts. 3(5), 15(3))
Pt. 3 (ss. 55-106) applied (7.6.2006) by Planning and Compulsory Purchase Act 2004 (c. 5), ss. 89, 121, Sch. 4 para. 3(2) (with s. 111); S.I. 2006/1281, art. 2
Pt. 3 (ss. 55-106) modified (22.11.2006) by The Docklands Light Railway (Stratford International Extension) Order 2006 (S.I. 2006/2905), art. 17(1) (with art. 43)
Pt. 3 (ss. 55-106) modified (13.12.2006) by The Luton Dunstable Translink Order 2006 (S.I. 2006/3118), art. 18(1)
C2Pt. 3 (ss. 55-106) modified (4.5.2005) by The Telford Railfreight Terminal (Donnington) Order 2005 (S.I. 2005/1163), art. 25(2) (with art. 30)
Pt. 3 modified (23.8.2007) by The Docklands Light Railway (Capacity Enhancement and 2012 Games Preparation) Order 2007 (S.I. 2007/2297), art. 17(1) (with arts. 3(6), 12(3))
C3Pt. 3 modified (28.9.2007) by The London Gateway Logistics and Commercial Centre Order 2007 (S.I. 2007/2657), art. 27(1) (with art. 19, Sch. 3 para. 13(2))
C4Pt. 3 modified (22.7.2008) by Crossrail Act 2008 (c. 18), s. 10(1)
C5Pt. 3 modified (14.10.2008) by The Felixstowe Branch Line and Ipswich Yard Improvement Order 2008 (S.I. 2008/2512), art. 34(1) (with art. 36(3))
C6Pt. 3 modified (20.7.2010) by The Network Rail (Nuneaton North Chord) Order 2010 (S.I. 2010/1721), art. 28(1)
C7Pt. 3 modified (27.8.2010) by The Llangollen and Corwen Railway Order 2010 (S.I. 2010/2136), art. 11(1)
C8Pt. 3 applied (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), arts. 1, 47(1) (with art. 51, Sch. 10 paras. 68, 85)
C9Pt. 3 modified (21.4.2011) by The Network Rail (Hitchin (Cambridge Junction)) Order 2011 (S.I. 2011/1072), arts. 1, 36(2)
Textual Amendments
F1Words in s. 97 cross-heading inserted (13.7.2016) by Housing and Planning Act 2016 (c. 22), s. 216(3), Sch. 12 para. 24; S.I. 2016/733, reg. 3(d)
(1)This section applies where—
(a)the local planning authority have made an order under section 97; and
(b)the owner and the occupier of the land and all persons who in the authority’s opinion will be affected by the order have notified the authority in writing that they do not object to it.
(2)Where this section applies, instead of submitting the order to the Secretary of State for confirmation the authority shall advertise in the prescribed manner the fact that the order has been made, and the advertisement must specify—
(a)the period within which persons affected by the order may give notice to the Secretary of State that they wish for an opportunity of appearing before, and being heard by, a person appointed by the Secretary of State for the purpose; and
(b)the period at the expiration of which, if no such notice is given to the Secretary of State, the order may take effect by virtue of this section without being confirmed by the Secretary of State.
(3)The authority shall also serve notice to the same effect on the persons mentioned in subsection (1)(b).
(4)The period referred to in subsection (2)(a) must not be less than 28 days from the date the advertisement first appears.
(5)The period referred to in subsection (2)(b) must not be less than 14 days from the expiration of the period referred to in subsection (2)(a).
(6)The authority shall send a copy of any advertisement published under subsection (2) to the Secretary of State not more than three days after the publication.
(7)If—
(a)no person claiming to be affected by the order has given notice to the Secretary of State under subsection (2)(a) within the period referred to in that subsection, and
(b)the Secretary of State has not directed within that period that the order be submitted to him for confirmation,
the order shall take effect at the expiry of the period referred to in subsection (2)(b), without being confirmed by the Secretary of State as required by section 98(1).
(8)This section does not apply—
(a)to an order revoking or modifying a planning permission [F2or permission in principle] granted or deemed to have been granted by the Secretary of State [F3or the Welsh Ministers] under this Part or Part VII, or
(b)to an order modifying any conditions to which a planning permission is subject by virtue of section 91 or 92.
Textual Amendments
F2Words in s. 99(8)(a) inserted (13.7.2016) by Housing and Planning Act 2016 (c. 22), s. 216(3), Sch. 12 para. 26; S.I. 2016/733, reg. 3(d)
F3Words in s. 99(8)(a) inserted (6.9.2015 for specified purposes, 1.3.2016 for specified purposes) by Planning (Wales) Act 2015 (anaw 4), s. 58(2)(b)(4)(b), Sch. 4 para. 12; S.I. 2016/52, art. 3(e)