Planning (Listed Buildings and Conservation Areas) Act 1990, Section 26K is up to date with all changes known to be in force on or before 26 December 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)Where an application is made to a local planning authority for a certificate under section 26H and—
(a)the application is refused or is refused in part, or
(b)the authority do not give notice to the applicant of their decision on the application within such period as may be prescribed under section 26I or within such extended period as may at any time be agreed in writing between the applicant and the authority,
the applicant may by notice appeal to the Secretary of State.
(2)A notice of appeal under this section—
(a)must be served within such time and in such manner as may be prescribed;
(b)must be accompanied by such information as may be prescribed.
(3)The time prescribed for the service of a notice of appeal under this section must not be less than—
(a)28 days from the date of notification of the decision on the application; or
(b)in the case of an appeal under subsection (1)(b), 28 days from—
(i)the end of the period prescribed as mentioned in subsection (1)(b), or
(ii)as the case may be, the extended period mentioned in subsection (1)(b).
(4)On an appeal under this section, the Secretary of State must grant the appellant a certificate under section 26H or, in the case of a refusal in part, modify the certificate granted by the authority on the application, if and so far as the Secretary of State is satisfied—
(a)in the case of an appeal under subsection (1)(a), that the authority's refusal is not well-founded, or
(b)in the case of an appeal under subsection (1)(b), that if the authority had refused the application their refusal would not have been well-founded.
(5)If and so far as the Secretary of State is satisfied that the authority's refusal is or, as the case may be, would have been well-founded, the Secretary of State must dismiss the appeal.
(6)Where the Secretary of State grants a certificate under section 26H on an appeal under this section, the Secretary of State must give notice to the local planning authority of that fact.
(7)References in this section to a refusal of an application in part include a modification or substitution of the description in the application of the works concerned.
(8)Schedule 3 applies to an appeal under this section.]
Textual Amendments
F1Ss. 26H-26K and cross-heading inserted (25.4.2013 for specified purposes, 6.4.2014 in so far as not already in force) by Enterprise and Regulatory Reform Act 2013 (c. 24), ss. 61, 103(1)(i)(3); S.I. 2014/416, art. 3(b)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: