- Latest available (Revised)
- Original (As enacted)
New Roads and Street Works Act 1991, Paragraph 11 is up to date with all changes known to be in force on or before 02 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
11(1)In relation to a toll order which is subject to special parliamentary procedure—E+W
(a)if the order is confirmed by Act of Parliament under section 6 of the M1Statutory Orders (Special Procedure) Act 1945, paragraph 10 above does not apply;
(b)in any other case, that paragraph has effect subject to the following modifications—
(i)the reference in sub-paragraph (1) to the date on which the notice required by paragraph 8 is published (or first published) shall be construed as a reference to the date on which the order becomes operative under the Act of 1945, and
(ii)in sub-paragraph (5) the words “and shall become operative” to the end shall be omitted.
(2)The provisions of paragraph 10(1) to (3) and (5) above apply in relation to a certificate under paragraph 9 as in relation to a toll order, subject to the following modifications—
(a)the reference in sub-paragraph (1) to the notice required by paragraph 8 shall be construed as a reference to the notice required by paragraph 9(3), and
(b)in sub-paragraph (5) for “made or confirmed” substitute “ given ” and omit the words from “and shall become operative” to the end.
Marginal Citations
M19 & 10 Geo. 6 c. 18.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: