SCHEDULE 4E+W Streets with special engineering difficulties
Modifications etc. (not altering text)
C1Sch. 4 modified (27.11.1992) by S.I. 1992/2984, art. 3(2)
IntroductoryE+W
1E+WIn this Schedule a “street with special engineering difficulties” means a street for the time being designated under section 63 as having special engineering difficulties.
Requirement of plan and sectionE+W
2(1)In a street with special engineering difficulties street works (other than emergency works) involving—E+W
(a)breaking up or opening the street, or any sewer, drain or tunnel under it, or
(b)tunnelling or boring under the street,
shall not be executed until a plan and section of the works have been settled by agreement between the undertaker and each of the relevant authorities or by arbitration.
(2)For that purpose an undertaker proposing to execute any such works shall submit a plan and section of them to each relevant authority.
3E+WEmergency works may be executed without a plan and section being so submitted or settled, but as soon as is reasonably practicable after the execution of the works the undertaker shall furnish a plan and section of the works to each relevant authority.
4(1)In the case of a street which is not a maintainable highway and which the street managers have no liability to the public to maintain or repair, the undertaker may give the street managers a notice stating—E+W
(a)the general effect of the works proposed or, as the case may be, of the emergency works executed, and
(b)that it is a notice given for the purposes of this paragraph.
(2)Where such a notice is given paragraphs 2 and 3 do not apply if the street managers do not, within 10 working days from the date on which the notice was given to them, give notice to the undertaker requiring the submission or furnishing of a plan and section to them.
5(1)A relevant authority to whom a plan and section of works are required to be submitted or furnished may accept as, or in lieu of, a plan and section any description of the works, whether in diagram form or not, which appears to them to be sufficient.E+W
(2)References in this Schedule to a plan and section include any such description so submitted or furnished to the form of which the relevant authority have not objected within the time allowed under paragraph 7(2) below.
6E+WIf an undertaker—
(a)executes any works in contravention of paragraph 2, or
(b)fails to furnish a plan and section in accordance with paragraph 3,
he commits an offence and is liable on summary conviction to a fine not exceeding level 3 on the standard scale.
Procedure on submission of plan and sectionE+W
7(1)A relevant authority to whom there is submitted a plan and section of street works proposed to be executed in a street with special engineering difficulties shall give notice to the undertaker—E+W
(a)approving the plan and section without modification, or
(b)objecting to them in form as being on too small a scale or giving insufficient particulars, or
(c)approving them subject to modifications specified in the notice, or
(d)disapproving them.
(2)The notice shall be given without avoidable delay, and at the latest before the end of the period of—
(a)7 working days in the case of a plan and section of works relating only to—
(i)a service pipe or service line, or
(ii)overhead electric lines or telecommunication apparatus, and
(b)one month in any other case;
and as between the undertaker and a relevant authority who do not duly give notice before the end of that period, the plan and section as submitted shall be deemed to have been settled by agreement.
(3)The reference in sub-paragraph (2)(a)(i) to a service pipe or service line is to—
(a)a pipe or line through or by means of which a supply of gas, electricity or water is afforded or intended to be afforded to premises—
(i)directly from premises from which the supply originates, or
(ii)from a main, that is, a pipe or line for affording a general supply;
(b)a pipe through or by means of which sewerage services are afforded, or intended to be afforded, which is a private sewer or drain within the meaning of the [F1Water Industry Act 1991]; or
(c)underground telecommunication apparatus for the purpose of providing a service by means of a telecommunication system to or from particular premises (as opposed to apparatus for the general purposes of such a system).
But so much of any such pipe, line or apparatus as is placed, or intended to be placed, for a continuous length of 100 metres or more in a maintainable highway shall be treated as not being a service pipe or service line.
(4)In this paragraph—
“electric line” has the same meaning as in Part I of the M1Electricity Act 1989;
“telecommunication apparatus” has the same meaning as in Schedule 2 to the M2Telecommunications Act 1984; and
“telecommunication system” has the meaning given by section 4(1) of that Act (read with subsection (2) of that section).
Textual Amendments
F1Words in Sch. 4 para. 7(3) substituted (01.12.1991) by Water Consolidation (Consequential Provisions) Act 1991 (c. 60, SIF 130), ss. 2(1), 4(2), Sch. 1 para. 57(2).
Marginal Citations
8(1)Where a relevant authority give notice approving the plan and section subject to modifications, or disapproving the plan and section, they shall state their reasons for doing so.E+W
(2)If a relevant authority duly give notice—
(a)objecting to the plan and section in form, or
(b)approving them subject to modifications to which the undertaker does not agree, or
(c)disapproving them,
then, unless the notice is withdrawn, the undertaker may refer the matter to arbitration.
(3)If the notice is withdrawn, the plan and section as submitted shall be deemed to have been settled by agreement between the relevant authority and the undertaker.
9E+WA sewer authority or bridge authority may not give notice—
(a)approving a plan and section subject to modifications, or
(b)disapproving a plan and section,
on grounds other than such as relate to the injurious effect of the proposed works on their sewer or, as the case may be, on the structure or stability of their bridge.
Settlement of plan and section by arbitrationE+W
10(1)The duty of the arbitrator where a matter is referred to arbitration is to settle a plan and section of works of the kind proposed, as works to be executed in the street.E+W
(2)He may require the undertaker to submit to him a plan and section in such form, require the relevant authority to submit to him such observations on a plan and section submitted to him, and require the undertaker or the relevant authority to furnish him with such information and to take such other steps, as appear to him to be requisite.
(3)He may treat compliance with any such requirement made of the undertaker as a condition of his proceeding with the settlement of a plan and section, and compliance with any such requirement made of the relevant authority as a condition of his settling a plan and section otherwise than as proposed by the undertaker.
11(1)Where the reference relates to the placing, altering or changing the position of apparatus in a street which is carried or crossed by a bridge, then, if the arbitrator is satisfied—E+W
(a)that the execution of the works would be likely to affect injuriously the structure or stability of the bridge, and
(b)that it is not practicable to meet objection on that ground to the plan and section submitted,
he shall so declare, and shall not settle any plan and section of those works on the reference.
(2)This does not affect the right of the undertaker to submit another plan and section.
Objection to works executed without plan and section being settledE+W
12(1)This paragraph applies where street works have been executed in a street with special engineering difficulties without a plan and section having been settled with the street authority or another relevant authority, whether the works were executed in contravention of paragraph 2 above or were emergency works.E+W
(2)The authority in question may, by notice to the undertaker, object to any of the works; and after affording the undertaker an opportunity to enter into an agreement with them for meeting the objection, may refer the matter to arbitration.
(3)The arbitrator may direct the alteration of the works to conform to a plan and section settled by him, or the removal of any apparatus placed in the execution of the works, and the undertaker shall comply with any such direction.
(4)In settling the terms of any such direction the arbitrator shall satisfy himself that compliance with it will not involve any undue interruption or restriction of the supply or service for the purposes of which the works were executed.
(5)If an undertaker fails to execute works in accordance with a direction under this paragraph, he commits an offence and is liable on summary conviction to a fine not exceeding level 3 on the standard scale.
Execution of works in accordance with plan and sectionE+W
13(1)An undertaker executing street works in a street with special engineering difficulties shall, where a plan and section have been settled, execute the works in accordance with the plan and section as settled or, if each of the relevant authorities agrees to the modification of the plan or section, in accordance with them as so modified.E+W
(2)If an undertaker fails to comply with sub-paragraph (1) he commits an offence and is liable on summary conviction to a fine not exceeding level 3 on the standard scale.