116 Notice of emergency works.
(1)
(2)
An undertaker executing emergency works shall, if the works are of a kind in respect of which notice is required by section 114, give notice as soon as reasonably practicable, and in any event within two hours (or such other period as may be prescribed) of the works being begun F3....
F4(3A)
For the purposes of subsection (2) an undertaker gives notice by—
(a)
giving to each person to whom notice would be required to be given under section 114 a notice—
(i)
stating the undertaker's intention, or as the case may be, the fact that he has begun to execute the works, and
(ii)
containing such other information as may be prescribed, and
(b)
entering in the SRWR a copy of that notice.
(4)
An undertaker who fails to give notice in accordance with this section commits an offence and is liable on summary conviction to a fine not exceeding F5level 4 on the standard scale.
(5)
In proceedings against a person for such an offence it is a defence for him to show that the contravention was attributable—
(a)
to his not knowing the position, or not knowing of the existence, of another person’s apparatus, or
(b)
to his not knowing the identity or address of—
(i)
a relevant authority, or
(ii)
the person to whom any apparatus belongs,
and that his ignorance was not due to any negligence on his part or to any failure to make inquiries which he ought reasonably to have made.