C12C1C2C3C4C5C6C7C8C9C20C190C59C28C169C194C74C117C44C153C136C65C95C184C221C208C205C133C158C209C115C75C45C40C176C16C188C51C54C148C41C134C146C140C43C23C149C203C88C118C77C111C181C260C254C17C211C63C128C108C201C212C130C193C66C61C227C141C157C229C220C30C259C222C49C21C215C96C218C250C18C164C168C214Part III Street works in England and Wales

Annotations:
Modifications etc. (not altering text)
C1

Pt. 3 (ss. 48-106) applied (6.11.2000) by 2000 c. 26, s. 95, Sch. 6 para. 1(3); S.I. 2000/2957, art. 2(1), Sch. 1

Pt. 3 (ss. 48-106) modified (29.3.2001) by S.I. 2001/1348, art. 21(2)

Pt. 3 (ss. 48-106) amended (24.7.2001) by S.I. 2001/3627, art. 4(1)

C2

Definition in Pt. 3 (ss. 48-106) applied (1.12.1991) by Water Industry Act 1991 (c. 56, SIF 130), ss. 71-84, 162-172, 219(1), 223(2), Sch. 6 para. 6(3)(a).

C3

Definition in Pt. 3 (ss. 48-106) applied (1.12.1991) by Water Resources Act 1991 (c. 57, SIF 130), ss. 178, 221(1), 225(2), Sch. 22 para. 3(2).

C4

Pt. 3 excluded (16.3.1992) by Avon Weir Act 1992 (c. v), s. 6(3) (with s. 61(1))

C5

Pt. 3 modified (1.1.1993) by Pipelines Act 1962 (c. 58), s. 16(1) (as substituted (1.1.1993) by New Roads and Street Works Act 1991 (c. 22), s. 168(1), Sch. 8 Pt. 3 para. 101(3); S.I. 1992/2984, art. 2(2), Sch.2)

Pt. 3 modified (27.7.1993) by 1993 c. xv, s. 4(1)

Pt. 3 (ss. 48-106) excluded (27.7.1993) by 1993 c. xv, s. 4(2)

C6

Pt. 3 applied (with modifications) (21.7.1994) by 1994 c. xv, s. 4(1)

Pt. 3 applied (21.7.1994) by 1994 c. xv, s. 45(5)(a)

Pt. 3 excluded (21.7.1994) by 1994 c. xv, s. 21(2)

Pt. 3 restricted (21.7.1994) by 1994 c. xv, s. 4(2)

C7

Pt. 3 excluded (18.12.1996) by 1996 c. 61, s. 52, Sch. 15 para. 1(3)

Pt. 3 modified (18.12.1996) by 1996 c. 61, s. 3, Sch. 3 para. 8

C8

Pt. 3 extended (28.7.1998) by 1998 c. iv, s. 3

C9

Pt. 3 applied (27.8.1998) by S.I. 1998/1936, arts. 1, 41, Sch. 10 paras. 2(8), 3(2)

Pt. 3 modified (13.1.1999) by S.I. 1998/3269, art. 4(1)

C208

Pt. 3 modified (22.7.2008) by Crossrail Act 2008 (c. 18), Sch. 3 para. 8

C205

Pt. 3 excluded (22.7.2008) by Crossrail Act 2008 (c. 18), Sch. 17 para. 1(3)

C40

Pt. 3 applied (with modifications) (9.4.2013) by The Hinkley Point C (Nuclear Generating Station) Order 2013 (S.I. 2013/648), arts. 1, 9 (with arts. 48, 68, 79)

C188

Pt. 3 modified (20.11.2013) by The M1 Junction 10a (Grade Separation) Order 2013 (S.I. 2013/2808), arts. 1, 8(1)(2)

C193

Pt. 3 applied (with modifications) (2.1.2018) by The Boston Barrier Order 2017 (S.I. 2017/1329), arts. 1, 3(2) (with arts. 55-57, Sch. 8 para. 13)

Notice and co-ordination of works

C10C13C195C20C192C190C169C204C67C194C264C44C257C153C242C136C132C152C184C185C221C172C158C159C166C209C48C262C145C253C87C177C107C154C15C122C240C226C113C180C47C160C121C83C120C124C261C99C37C50C235C85C119C100C263C123C228C151C68C112C33C210C165C129C206C60C173C213C101C258C40C187C198C189C248C58C239C98C19C138C78C161C105C24C176C110C186C73C16C69C182C241C76C188C51C26C54C106C148C31C32C183C167C90C134C64C236C146C230C140C249C94C43C81C126C196C23C29C223C62C80C131C14C109C52C56C72C207C55C231C91C39C171C92C125C139C191C247C163C162C135C255C34C42C25C234C70C245C252C244C203C86C97C118C265C216C77C260C71C237C142C179C254C219C22C150C103C93C17C35C128C232C137C79C102C38C201C243C130C156C197C193C66C61C127C227C143C141C225C229C53C199C116C220C27C155C84C175C30C246C147C259C174C202C49C144C89C21C233C224C217C215C238C96C114C104C218C82C250C164C178C4656C20C190C59C28C169C194C74C117C44C153C136C184C221C208C205C158C209C115C40C176C16C188C51C54C148C134C146C140C43C23C203C118C77C260C254C17C211C63C128C201C130C193C66C61C227C141C229C220C30C259C49C21C215C96C218C250C164C168C214 Power to give directions as to timing of street works.

C11C57C200C251C256C36C1701

If it appears to the street authority—

a

that proposed street works are likely to cause serious disruption to traffic, and

b

that the disruption would be avoided or reduced if the works were carried out only at certain times F4or on certain days (or at certain times on certain days),

the authority may give the undertaker such directions as may be appropriate as to the times F4or days (or both) when the works may or may not be carried out.

C57C200C251C256C36C170F21A

Where it appears to a street authority—

a

that subsisting street works are causing or are likely to cause serious disruption to traffic, and

b

that the disruption would be avoided or reduced if the works were to continue to be carried out only at certain times or on certain days (or at certain times on certain days),

the authority may give the undertaker such directions as may be appropriate as to the times or days (or both) when the works may or may not continue to be carried out.

2

The procedure for giving a direction shall be prescribed by the Secretary of State.

3

An undertaker who executes works in contravention of a direction under this section commits an offence and is liable on summary conviction to a fine not exceeding F1level 5 on the standard scale.

F33A

An undertaker shall be taken not to have failed to fulfil any statutory duty to afford a supply or service if, or to the extent that, his failure is attributable to a direction under this section.

C114

The Secretary of State may issue or approve for the purposes of this section a code of practice giving practical guidance as to the exercise by street authorities of the power conferred by this section; and in exercising that power a street authority shall have regard to the code of practice.