Print Options
PrintThe Whole
Act
PrintThe Whole
Part
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Section 65


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Version Superseded: 06/04/2012
Status:
Point in time view as at 01/12/1991. This version of this provision has been superseded.

Status
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Changes to legislation:
There are currently no known outstanding effects for the Planning and Compensation Act 1991, Section 65.

Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
65 Certification of appropriate alternative development.E+W
(1)For section 17(1) of the Land Compensation Act 1961 (certificate of appropriate alternative development may be issued only if land is not in an area defined in development plan as an area of comprehensive development or shown in the plan as allocated for residential, commercial or industrial use) there is substituted—
“(1)Where an interest in land is proposed to be acquired by an authority possessing compulsory purchase powers, either of the parties directly concerned may, subject to subsection (2) of this section, apply to the local planning authority for a certificate under this section.”
(2)In subsection (4) of that section (certificate stating that permission for development would or would not be granted) for paragraphs (a) and (b) there is substituted—
“(a)that planning permission would have been granted for development of one or more classes specified in the certificate (whether specified in the application or not) and for any development for which the land is to be acquired, but would not have been granted for any other development; or
(b)that planning permission would have been granted for any development for which the land is to be acquired, but would not have been granted for any other development,
and for the purposes of this subsection development is development for which the land is to be acquired if the land is to be acquired for purposes which involve the carrying out of proposals of the acquiring authority for that development. ”
(3)After subsection (9) of that section there is inserted—
“(9A)In assessing the compensation payable to any person in respect of any compulsory acquisition, there shall be taken into account any expenses reasonably incurred by him in connection with the issue of a certificate under this section (including expenses incurred in connection with an appeal under section 18 of this Act where any of the issues on the appeal are determined in his favour).”