Search Legislation

Water Industry Act 1991

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: Cross Heading: Provision of sewerage services by sewerage licensees etc

 Help about opening options

Alternative versions:

Status:

Point in time view as at 09/01/2022.

Changes to legislation:

Water Industry Act 1991, Cross Heading: Provision of sewerage services by sewerage licensees etc is up to date with all changes known to be in force on or before 29 December 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.

[F1Provision of sewerage services by sewerage licensees etcE+W

Textual Amendments

F1Ss. 110K-110O and cross-heading inserted (6.3.2017 for the insertion of s. 110K, 1.4.2017 in so far as not already in force) by Water Act 2014 (c. 21), ss. 32, 94(3); S.I. 2017/58, art. 2(a) (with art. 3(2)); S.I. 2017/462, art. 3(g)

110KProvision by sewerage licenseeE+W

(1)The owner or occupier of any premises may serve a notice on a sewerage undertaker—

(a)informing the undertaker that sewerage services to the premises are to be provided by a sewerage licensee, and

(b)specifying the time after which the undertaker will no longer be required to provide sewerage services to the premises.

(2)Where the charges for the sewerage services provided by the undertaker are, under Chapter 1 of Part 5 of this Act, fixed in relation to the premises by reference to volume, the time specified in the notice is to fall at least two working days after the notice is served.

(3)In this section a reference to two working days is a reference to a period of 48 hours calculated after disregarding any time falling on—

(a)a Saturday or Sunday, or

(b)Christmas Day, Good Friday or any day which is a bank holiday in England and Wales under the Banking and Financial Dealings Act 1971.

110LInterim duty: sewerage undertakers and sewerage licenseesE+W

(1)This section applies where—

(a)a sewerage licensee (“the previous licensee”) ceases to provide sewerage services to any premises, and

(b)the owner or occupier of the premises has not notified the sewerage undertaker in whose area the premises are that—

(i)he has made arrangements for the continuation of the provision of sewerage services to the premises, or

(ii)he intends any provision of sewerage services to the premises to cease.

(2)It is to be the duty of the sewerage undertaker to continue to provide the sewerage services to the premises which were provided by the previous licensee.

(3)But the Authority may give a direction to an eligible sewerage licensee (an “interim licensee”) providing that it is to be the duty of that licensee to provide the sewerage services instead.

[F2(3A)Where the premises are in a retail exit area the Authority must give a direction under subsection (3).]

(4)An “eligible sewerage licensee” is a sewerage licensee with a retail authorisation who has elected to be an eligible sewerage licensee for the purposes of this section in accordance with the code issued under section 110O.

(5)If the Authority proposes to give a direction under subsection (3) to an eligible sewerage licensee—

(a)the Authority must give notice of the proposed direction to the licensee, and

(b)the licensee may, in accordance with the code issued under section 110O, temporarily suspend the election made by the licensee as mentioned in subsection (4), so that the proposed direction cannot be given to the licensee.

(6)Where sewerage services are provided by an undertaker under subsection (2)—

(a)the charges payable in respect of the provision of the services are to be fixed from time to time by a charges scheme under section 143, and

(b)the services are to be provided until—

(i)services are provided by an interim licensee by virtue of a direction under subsection (3),

(ii)services are provided by a sewerage licensee following the service of a notice under section 110K, or

(iii)services are provided to the premises by another sewerage undertaker following the service of a notice by the owner or occupier of the premises on the undertaker providing services under subsection (2) specifying the time after which the undertaker will no longer be required to provide sewerage services to the premises (see section 110M(5)),

whichever is the earlier.

(7)Where sewerage services are provided by an interim licensee by virtue of a direction given under subsection (3)—

(a)the provision of services by the interim licensee is to be treated as having begun on the date on which the previous licensee ceased to provide services to the premises,

(b)the terms and conditions in accordance with which the services are to be provided are to be—

(i)those provided for by a scheme made under section 110N, or

(ii)such other terms and conditions as may be agreed between the interim licensee and the owner or occupier of the premises, and

(c)the services are to be provided until they are discontinued in accordance with the terms and conditions mentioned in paragraph (b).

(8)Subsections (9) and (10) apply if, within a period of three months beginning with the date on which the previous licensee ceased to provide sewerage services to the premises, the owner or occupier of the premises serves notice—

(a)under section 110K, on the sewerage undertaker continuing the provision of services under subsection (2), or

(b)in accordance with the terms and conditions mentioned in subsection (7)(b), on the interim licensee continuing the provision of services by virtue of a direction given under subsection (3),

that instead another sewerage licensee (“the new licensee”) is to continue the provision of the services to the premises which were provided by the previous licensee.

(9)The notice must—

(a)specify the time from which the new licensee is to continue the provision of the services in question, and

(b)be served in accordance with the code issued under section 110O.

(10)In the case of a notice served as mentioned in subsection (8)(a), the provision of services by the new licensee is to be treated as having begun on the date on which the previous licensee ceased to provide services to the premises.

110MInterim duty: supplementaryE+W

(1)Where a duty is imposed by section 110L(2), or by virtue of a direction given under section 110L(3), in respect of any premises, any breach of the duty which causes the owner or occupier of the premises to sustain loss or damage is actionable at the suit of that owner or occupier.

(2)But in any proceedings brought against a sewerage undertaker or sewerage licensee in pursuance of subsection (1), it is a defence for the undertaker or licensee to show that the undertaker or, as the case may be, the licensee took all reasonable steps and exercised all due diligence to avoid the breach.

(3)For the purposes of section 110L, premises which are outside a sewerage undertaker's area are to be treated as being within that area if they are provided with sewerage services using the undertaker's sewerage system.

(4)In subsection (3), the reference to the undertaker's sewerage system is to be construed in accordance with section 17BA(7).

(5)Section 110K(2) and (3) apply to a notice served under section 110L(6)(b)(iii) as they apply to a notice served under section 110K.

110NInterim licensees: schemes for terms and conditionsE+W

(1)A person who is an eligible sewerage licensee for the purposes of section 110L must make, and from time to time revise, a scheme containing the terms and conditions which, in the absence of agreed terms and conditions, are to apply to the provision of sewerage services by the licensee by virtue of a direction given under section 110L(3).

(2)A scheme under this section may make different provision for different purposes, or for different areas.

(3)As soon as practicable after a sewerage licensee makes or revises a scheme under this section the licensee is to—

(a)publish the scheme, or revised scheme, on the licensee's website, and

(b)send a copy of the scheme, or revised scheme, to the Authority.

(4)The Authority may give a direction that terms and conditions applying to the provision of sewerage services in accordance with a scheme under this section must be modified as specified in the direction.

(5)A direction under subsection (4) may apply—

(a)generally to terms and conditions applying in accordance with a scheme under this section, or

(b)to terms and conditions so applying in any particular case.

(6)It is the duty of a sewerage licensee to comply with a direction under subsection (4), and this duty is enforceable under section 18.

110OInterim duty: codeE+W

(1)The Authority must issue a code in relation to—

(a)the provision of sewerage services under section 110L, and

(b)its power of direction under section 110L(3) (power to direct that eligible sewerage licensee provides interim sewerage services).

(2)The code may, in particular, make provision about—

(a)the procedure for electing to be an eligible sewerage licensee for the purposes of section 110L;

(b)the procedure for temporarily suspending such an election under section 110L(5)(b);

(c)the circumstances in which the Authority's power of direction under section 110L(3) or 110N(4) may or may not be exercised;

(d)how the Authority will determine the date on which a sewerage licensee ceased to provide sewerage services to premises for the purposes of section 110L;

(e)terms and conditions contained in schemes made under section 110N;

(f)eligible sewerage licensees informing owners or occupiers of premises of their schemes for terms and conditions made under section 110N, before agreeing any terms and conditions as mentioned in section 110L(7)(b)(ii);

(g)the giving of notices as mentioned in section 110L(8) (that a new licensee is to continue the provision of the sewerage services provided by the previous licensee) including, in particular, provision about—

(i)the earliest time that a notice may specify as the time from which a new licensee is to continue the provision of the sewerage services provided by a previous licensee;

(ii)the procedure for serving a notice.

(3)If the Authority considers that a sewerage licensee is not acting as required by provision contained in the code as mentioned in subsection (2)(e) or (f), the Authority may give the licensee a direction to do, or not to do, a particular thing specified in the direction.

(4)It is the duty of a sewerage licensee to comply with a direction under subsection (3), and this duty is enforceable under section 18.

(5)The Authority must from time to time review the code and, if appropriate, issue a revised code.

(6)References in section 110L to the code issued under this section are to the code issued under this section that has effect at the time in question.]

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act without Schedules as a PDF

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources