C1C2 Part IV SEWERAGE SERVICES

Annotations:
Modifications etc. (not altering text)
C1

Pt. IV: power to apply conferred (1.12.1991) by Water Resources Act 1991 (c. 57, SIF 130), ss. 78(2)(b), 225(2).

chapter II PROVISION OF SEWERAGE SERVICES

Requisition of public sewer

F1101 Determination of completion date and route for requisitioned sewer or lateral drain.

1

A sewerage undertaker shall not be in breach of a duty imposed by section 98 above in relation to any locality or (in the case of a lateral drain) in relation to any premises unless—

a

the period of six months beginning with the relevant day has expired; and

b

the sewerage undertaker has not, before the end of that period, so laid (as the case may be)—

i

the public sewer to be provided as to enable drains and private sewers to be used for the drainage of premises in the locality to communicate with the public sewer; or

ii

the lateral drain to be provided as to enable the drain to be used for the drainage of premises to communicate with a public sewer vested in that undertaker,

at the place or places determined under subsection (3) below.

2

The period mentioned in subsection (1)(a) above may be extended—

a

by agreement between the undertaker and the person or persons who required the provision of the public sewer or, as the case may be, lateral drain; or

b

where there is a dispute as to whether the period should be extended, by the Authority on a reference under subsection (4) below.

3

The places mentioned in subsection (1)(b) above shall be—

a

such place or places as are determined by agreement between the sewerage undertaker and the person or persons who required the provision of the public sewer or, as the case may be, lateral drain; or

b

in default of agreement, such place or places as are determined by the Authority on a reference under subsection (4) below to be the place or places at which it is reasonable, in all the circumstances—

i

in relation to the provision of a public sewer, for drains or private sewers to be used for the drainage of premises in the locality in question to communicate with the public sewer; or

ii

in relation to the provision of a lateral drain—

a

for the lateral drain to communicate with a public sewer vested in the undertaker; and

b

for the remainder of the drain of which the lateral drain forms part to connect with the lateral drain.

4

A reference for the purposes of subsection (2) or (3) above may be made to the Authority for determination under section 30A above by either party to the dispute.

5

In this section “relevant day”, in relation to a requirement to provide a public sewer for any locality or, as the case may be, a lateral drain, means the day after whichever is the later of the following—

a

the day on which the conditions specified in section 99 above are satisfied in relation to the requirement; and

b

the day on which the place or places where (as the case may be)—

i

drains or private sewers to be used for the drainage of premises in that locality will communicate with the public sewer; or

ii

the lateral drain will communicate with a public sewer and the remainder of the drain will connect with the lateral drain,

are determined under subsection (3) above.