C1C2 Part IV SEWERAGE SERVICES

Annotations:
Modifications etc. (not altering text)
C1

Pt. IV: power to apply conferred (1.12.1991) by Water Resources Act 1991 (c. 57, SIF 130), ss. 78(2)(b), 225(2).

C3F1Chapter 2ADuties relating to sewerage services: sewerage licensees

Annotations:
Amendments (Textual)
F1

Pt. 4 Ch. 2A inserted (1.9.2015 for the insertion of s. 117G (except s. 117G(2)(e)(7)), 1.9.2015 for the insertion of s. 117K (except s. 117K(2)(e)(8)), 1.4.2016 for the insertion of ss. 117G(2)(e), 117P(4), 117R, 117S, 1.9.2016 for the insertion of ss. 117I for specified purposes, 117J, 117K(2)(e)(8), 117L, 30.3.2017 for the insertion of s. 117G so far as not already in force and ss. 117F, 117H) by Water Act 2014 (c. 21), s. 94(3), Sch. 4; S.I. 2015/773, art. 3(d) (with art. 5); S.I. 2015/1469, art. 3(e); S.I. 2016/465, arts. 2(k), 3(f) (with Sch. 2) (as amended (22.3.2017) by S.I. 2017/462, art. 16); S.I. 2017/462, art. 2(d)

Modifications etc. (not altering text)

Duties of sewerage undertakers as regards enabling the provision of sewerage services

117ODesignation of collective strategic sewerage provision

1

Subsection (2) applies if at any time the Authority determines that two or more cases of the removal of matter from a sewerage system—

a

each of which is a removal by a sewerage licensee, and

b

each of which is a removal that a sewerage undertaker is required to permit under section 117C or 117D in accordance with a section 117E agreement,

constitute collective strategic sewerage provision.

2

The Authority must designate the cases of the removal of matter as collective strategic sewerage provision.

3

Subsection (4) applies if—

a

a sewerage undertaker requests the Authority to make a determination that two or more cases of the removal of matter from a sewerage system constitute collective strategic sewerage provision for the purposes of subsection (1), or

b

the Authority otherwise proposes to make a determination that two or more cases of the removal of matter from a sewerage system constitute collective strategic sewerage provision for the purposes of subsection (1).

4

The Authority must give notice of the request or proposed determination to—

a

the Secretary of State;

b

the appropriate agency;

c

the other party or parties, or the parties, to the section 117E agreements in question; and

d

such other persons (if any) as the Authority thinks it appropriate to notify.

5

A notice under subsection (4) must specify the time within which representations or objections with respect to the request or proposed determination may be made.

The time specified may not be less than 28 days from the date on which the notice was given.

6

The Authority must consider any representations or objections which are duly made and not withdrawn.

7

If the Authority determines that the cases of the removal of matter from a sewerage system designated under this section as collective strategic sewerage provision no longer constitute such provision, it must cancel their designation.

8

If the Authority proposes to make a determination under subsection (7) that the cases of the removal of matter from a sewerage system no longer constitute collective strategic sewerage provision, it must give notice of the proposed determination to—

a

the Secretary of State;

b

the appropriate agency; and

c

the parties to the section 117E agreements in question.

9

Subsection (5) applies to a notice under subsection (8) as it applies to a notice under subsection (4), and subsection (6) applies accordingly.

10

For the purposes of this section, two or more cases of the removal of matter from a sewerage system are collective strategic sewerage provision if, without those cases of the removal of matter, there is a substantial risk that the sewerage undertaker would be unable—

a

to maintain its services to its own customers, and

b

to fulfil its obligations under section 117B to deal with matter in its sewerage system.