- Latest available (Revised)
- Point in Time (23/09/2016)
- Original (As enacted)
Version Superseded: 01/11/2016
Point in time view as at 23/09/2016. This version of this provision has been superseded.
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Water Industry Act 1991, Section 40A is up to date with all changes known to be in force on or before 19 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)On the application of any party to a bulk supply agreement, the Authority may—
(a)if it appears to the Authority that it is necessary or expedient for the purpose of securing the efficient use of water resources, or the efficient supply of water, that the bulk supply agreement should be varied or terminated, and
(b)if the Authority is satisfied that variation or termination cannot be achieved by agreement within a reasonable time,
by order vary or terminate the bulk supply agreement.
(2)Before making an order under subsection (1), the Authority must consult the appropriate agency, in particular about whether the proposed variation or termination of the bulk supply agreement would secure an efficient use of water resources, taking into account the effect on the environment of what is proposed.
(3)If an order under subsection (1) is made in relation to a bulk supply agreement, the agreement—
(a)has effect subject to the provision made by the order, or
(b)ceases to have effect (as the case may be).
(4)An order under subsection (1) may require any party to the agreement to pay compensation to any other party.
(5)Neither the CMA nor the Authority may exercise, in respect of an agreement to vary or terminate a bulk supply agreement, the powers conferred by—
(a)section 32 of the Competition Act 1998 (directions in relation to agreements);
(b)section 35(2) of that Act (interim directions).
(6)Subsection (5)(b) does not apply to the exercise of powers in respect of conduct—
(a)which is connected with an agreement to vary or terminate a bulk supply agreement, and
(b)in respect of which section 35(1) of the Competition Act 1998 applies because of an investigation under section 25 of that Act relating to a suspected infringement of the Chapter 2 prohibition imposed by section 18(1) of that Act.
(7)In exercising its functions under this section, the Authority must have regard to the expenses incurred by the supplier in complying with its obligations under the bulk supply agreement in question and to the desirability of—
(a)facilitating effective competition within the water supply industry;
(b)the supplier's recovering the expenses of complying with its obligations by virtue of this section and securing a reasonable return on its capital;
(c)the supplier's being able to meet its existing obligations, and likely future obligations, to supply water without having to incur unreasonable expenditure in carrying out works;
(d)not putting at risk the ability of the supplier to meet its existing obligations, or likely future obligations, to supply water.
(8)In this section and sections 40B to 40J—
“qualifying person” has the meaning given by section 40;
“supplier”, in relation to a bulk supply agreement, means any water undertaker which is required by the agreement to provide a bulk supply of water.]
Textual Amendments
F1Ss. 40-40J substituted for ss. 40, 40A (6.4.2015 for the insertion of s. 40J) by Water Act 2014 (c. 21), ss. 8(1), 94(3) (with s. 8(2)); S.I. 2015/773, art. 2(1)(a)(i) (with art. 4)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: