This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 09/01/2022.
Changes to legislation:
There are outstanding changes not yet made by the legislation.gov.uk editorial team to Water Industry Act 1991. Any changes that have already been made by the team appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
49 Supplemental provisions with respect to the metering conditions.E+W
(1)The power conferred on a water undertaker to impose conditions under section 47 above for the purposes of metering—
(a)shall be exercisable in relation to any premises even if the undertaker has no immediate intention, when the power is exercised, of fixing charges in relation to those premises by reference to volume; but
(b)shall not be exercisable so as to require the alteration or removal of any pipe laid or plumbing installed before 1st April 1989.
(2)Specifications approved by any water undertaker for the purposes of subsection (2)(c) or (d) of section 47 above may be approved—
(a)in relation to particular premises; or
(b)by being published in such manner as the undertaker considers appropriate, in relation to premises generally or to any description of premises.
[(3)Any dispute between a water undertaker and any other person as to the terms of any condition imposed under section 47 above for the purposes of metering shall be referred—
(a)to the arbitration of a single arbitrator appointed by agreement between the undertaker and that person; or
(b)if no agreement is reached, for determination by [the Authority] under section 30A above.]
(4)References in this section to the imposition of a condition under section 47 above for the purposes of metering are references to the imposition of conditions by virtue of subsection (2)(c) or (d) of that section.