Search Legislation

Water Resources Act 1991

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: chapter III

 Help about opening options

Alternative versions:

Status:

Point in time view as at 06/04/2016.

Changes to legislation:

There are currently no known outstanding effects for the Water Resources Act 1991, chapter III. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

chapter IIIE+W PROVISIONS SUPPLEMENTAL TO LAND AND WORK POWERS

Vesting of pipes in the [F1appropriate agency] E+W

175 Vesting of pipes in the [F2appropriate agency].E+W

(1)Subject to any provision to the contrary contained in an agreement between the [F2appropriate agency] and the person in whom an interest in the pipe is or is to be vested, every pipe which—

(a)is a relevant pipe for the purposes of section 159 or 160 above; and

(b)has been laid, in exercise of any power conferred by Chapter I of this Part or otherwise, by the [F2appropriate agency],

shall vest in the [F2appropriate agency].

(2)Subsection (1) above is without prejudice to the vesting of anything in the [F2appropriate agency] by virtue of the exercise by the [F2appropriate agency] of any power to acquire property by agreement or compulsorily.

Offence of interference with works etc.E+W

176 Offence of interference with works etc.E+W

(1)Subject to subsection (2) below, if any person without the consent of the [F3appropriate agency]

(a)intentionally or recklessly interferes with any resource main or other pipe vested in the [F3appropriate agency] or with any structure, installation or apparatus belonging to the [F3appropriate agency]; or

(b)by any act or omission negligently interferes with any such main or other pipe or with any such structure, installation or apparatus so as to damage it or so as to have an effect on its use or operation,

that person shall be guilty of an offence and liable, on summary conviction, to a fine not exceeding level 3 on the standard scale.

(2)A person shall not be guilty of an offence under subsection (1) above—

(a)by reason of anything done in an emergency to prevent loss or damage to persons or property; or

(b)by reason of his opening or closing the stopcock fitted to a service pipe by means of which water is supplied to any premises by a water undertaker if—

(i)he has obtained the consent of every consumer whose supply is affected by the opening or closing of that stopcock or, as the case may be, of every other consumer whose supply is so affected; and

(ii)in the case of opening a stopcock, the stopcock was closed otherwise than by the undertaker.

(3)Any person who without the consent of the [F3appropriate agency]

(a)attaches any pipe or apparatus to any resource main or other pipe vested in the [F3appropriate agency]; or

(b)subject to subsection (4) below, uses any pipe or apparatus which has been attached or altered in contravention of this section,

shall be guilty of an offence and liable, on summary conviction, to a fine not exceeding level 3 on the standard scale.

(4)In proceedings against any person for an offence by virtue of paragraph (b) of subsection (3) above it shall be a defence for that person to show that he did not know, and had no grounds for suspecting, that the pipe or apparatus in question had been attached or altered as mentioned in that subsection.

(5)An offence under subsection (1) or (3) above shall constitute a breach of a duty owed to the [F3appropriate agency]; and any such breach of duty which causes the [F3appropriate agency] to sustain loss or damage shall be actionable at the suit of the [F3appropriate agency].

(6)The amount recoverable by virtue of subsection (5) above from a person who has committed an offence under subsection (3) above shall include such amount as may be reasonable in respect of any water wasted, misused or improperly consumed in consequence of the commission of the offence.

(7)In this section “service pipe” and “stopcock” have the same meanings as in the M1Water Industry Act 1991, and “consumer” has the same meaning as in Part III of that Act.

Textual Amendments

Marginal Citations

Compensation etc. in respect of exercise of works powersE+W

177 Compensation etc. in respect of exercise of works powers.E+W

Schedule 21 to this Act shall have effect for making provision for imposing obligations as to the payment of compensation in respect of the exercise of the powers conferred on the [F3appropriate agency] by sections 159 to 167 above and otherwise for minimising the damage caused by the exercise of those powers.

Textual Amendments

Protective provisionsE+W

178 Protection for particular undertakings.E+W

Schedule 22 to this Act shall have effect for the protection of particular undertakings in connection with the carrying out of works and other activities by the [F3appropriate agency].

Textual Amendments

179 Protective provisions in respect of flood defence works and watercourses etc.E+W

(1)Nothing in this Act shall confer power on any person to do anything, except with the consent of the person who so uses them, which interferes—

(a)with any sluices, floodgates, groynes, sea defences or other works used by any person for draining, preserving or improving any land under any local statutory provision; or

(b)with any such works used by any person for irrigating any land.

(2)Where the [F3appropriate agency] proposes, otherwise than in exercise of any compulsory powers—

(a)to construct or alter any such inland waters in any internal drainage district as do not form part of a main river; or

(b)to construct or alter any works on or in any such inland waters,

the [F3appropriate agency] shall consult the internal drainage board for that district before doing so.

(3)A consent for the purposes of subsection (1) above may be given subject to reasonable conditions but shall not be unreasonably withheld.

(4)Any dispute—

(a)as to whether anything done or proposed to be done interferes or will interfere as mentioned in subsection (1) above;

(b)as to whether any consent for the purposes of this section is being unreasonably withheld; or

(c)as to whether any condition subject to which any such consent has been given was reasonable,

shall be referred to the arbitration of a single arbitrator to be appointed by agreement between the parties or, in default of agreement, by the President of the Institution of Civil Engineers.

(5)The provisions of this section shall be without prejudice to the provisions of Schedule 22 to this Act.

Textual Amendments

Modifications etc. (not altering text)

C1S. 179 applied (01.12.1991) by Land Drainage Act 1991 (c. 59, SIF 73:1), ss. 67(2), 76(2).

180 Power of navigation authorities etc to divert the [F4appropriate agency's] watercourses.E+W

(1)Where any watercourses under the control of the [F4appropriate agency] pass under or interfere with, or with the improvement or alteration of, any river, canal, dock, harbour, basin or other work (including any towing-path adjacent thereto) which belongs to or is under the jurisdiction of any relevant authority, the relevant authority may, at their own expense and on substituting for those watercourses other equally effective watercourses—

(a)take up, divert or alter the level of those watercourses; and

(b)do all such matters and things as may be necessary in connection with the works authorised to be done by them under this section.

(2)If any question arises under this section between the [F4appropriate agency] and any relevant authority as to whether any watercourses substituted or proposed to be substituted by the relevant authority for any existing watercourses are as effective as the existing watercourses, that question shall be referred to the arbitration of a single arbitrator appointed by agreement between the parties or, in default of agreement, by the President of the Institution of Civil Engineers on the application of either party.

(3)In this section—

  • relevant authority” means any navigation authority, harbour authority or conservancy authority; and

  • watercourse” has the same meaning as in Part IV of this Act.

Textual Amendments

181 Works in tidal lands etc.E+W

(1)Nothing in any of the provisions of this Part relating to any relevant works power shall authorise the [F5appropriate agency] to carry out any works at any place below the place to which the tide flows at mean high water springs, except in accordance with such plans and sections, and subject to such restrictions, as may, before the works are commenced, have been approved by the Secretary of State.

(2)An approval for the purposes of subsection (1) above shall be given to the [F5appropriate agency] by the service on the [F5appropriate agency] of a notice containing the approval.

(3)Section 38 of the M2Salmon and Freshwater Fisheries Act 1975 (tidal lands etc.) shall apply to any proposed construction, alteration or extension under section 156 above as it applies to any proposed construction, alteration or extension under that Act.

(4)Section 74 of the M3Land Drainage Act 1991 (application to Crown and tidal lands), so far as it relates to lands below the high-water mark of ordinary spring tides shall apply, as it applies in relation to that Act, to the flood defence provisions of this Act.

(5)In subsection (1) above the reference to a relevant works power is a reference to a power conferred by any of sections 159, 160, 162(2) and (3) and 163 above.

Textual Amendments

Marginal Citations

182 Mineral rights.E+W

Schedule 23 to this Act (which makes provision with respect to the acquisition of mineral rights by the [F6appropriate agency] and with respect to the working of mines and minerals where pipes, sewers or other related works are affected) shall have effect and, in the case of the compulsory acquisition of land by virtue of this Act, shall have effect instead of Schedule 2 to the M4Acquisition of Land Act 1981 (mineral rights etc. in relation to compulsory purchase orders).

Textual Amendments

Marginal Citations

183 Saving for planning controls etc.E+W

(1)Without prejudice to the operation of section 90 of the M5Town and Country Planning Act 1990 (planning permission deemed to be granted in certain cases) in relation to any provision made by or under this Act or any other enactment which by virtue of this Act or the M6Water Act 1989 relates to the functions of the [F7appropriate agency], nothing in this Act or in any such enactment shall be construed as authorising the carrying out of any development (within the meaning of that Act of 1990) without the grant of such planning permission as may be required by that Act of 1990.

(2)Nothing in the flood defence provisions of this Act shall authorise any person to carry out any works or do anything in contravention of any of the provisions of the M7Ancient Monuments and Archaelogical Areas Act 1979.

Textual Amendments

Modifications etc. (not altering text)

C2S. 183 applied (01.12.1991) by Land Drainage Act 1991 (c. 59, SIF 73:1), ss. 67(2), 76(2).

Marginal Citations

184 Duties to make recreational facilities available when building reservoirs in Wales.W

(1)Where [F8the NRBW] carries out any works for or in connection with the construction or operation of a reservoir in Wales which—

(a)permanently affect one or more communities; and

(b)are not primarily intended by [F8the NRBW] to benefit the inhabitants of that or those communities,

it shall be the duty of [F8the NRBW] to make available facilities for recreation or other leisure-time occupation for the benefit of those inhabitants or to assist others to make such facilities available.

(2)It shall be the duty of [F8the NRBW], in performing its duty under subsection (1) above, to consult—

(a)the community councils of the communities affected, in the case of communities having such councils; and

(b)in any case, the council of any [F9county or county borough] in which any community affected is situated.

Savings in respect of existing drainage obligationsE+W

185 Savings in respect of existing drainage obligations.E+W

(1)Nothing in the flood defence provisions of this Act shall operate to release any person from an obligation to which section 21 of the M8Land Drainage Act 1991 applies.

(2)The functions of the [F10appropriate agency] as respects the doing of any work under the flood defence provisions of this Act are not to be treated as in any way limited by the fact that some other person is under an obligation, by reason of tenure, custom, prescription or otherwise, to do that work.

Interpretation of Part VIIE+W

186 Interpretation of Part VII.E+W

(1)In this Part—

  • discharge pipe” means a pipe from which discharges are or are to be made under section 163 above;

  • [F11“relevant transferred functions” means any functions which—

    (a)

    were exercisable by the Agency before 1 April 2013, and

    (b)

    are functions of the NRBW by virtue of the Natural Resources Body for Wales (Functions) Order 2013,

    but this is subject to subsection (1A).]

  • resource main” means any pipe, not being a trunk main within the meaning of the M9Water Industry Act 1991, which is or is to be used for the purpose of—

(a)conveying water from one source of supply to another, from a source of supply to a regulating reservoir or from a regulating reservoir to a source of supply; or

(b)giving or taking a supply of water in bulk.

[F12(1A)For the purposes of the definition of “relevant transferred functions”—

(a)a function of the Agency was exercisable before 1 April 2013 whether or not the enactment conferring it had come into force before that date, but

(b)a function is only a relevant transferred function when the enactment conferring the Agency function transferred to or conferred on the NRBW has come into force.]

(2)In subsection (1) above—

  • source of supply” shall be construed without reference to the definition of that expression in section 221 below; and

  • supply of water in bulk” has the same meaning as in section 3 above.

(3)The powers conferred by Chapter I of this Part shall be without prejudice to the powers conferred on the Agency [F13or on the NRBW] by any other enactment or by any agreement.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act without Schedules as a PDF

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources