Print Options
PrintThe Whole
Act
PrintThe Whole
Schedule
PrintThis
Cross Heading
only
Changes over time for: Cross Heading: Powers on an application


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Version Superseded: 01/04/2013
Status:
Point in time view as at 01/10/2005.
Changes to legislation:
There are outstanding changes not yet made by the legislation.gov.uk editorial team to Water Resources Act 1991. Any changes that have already been made by the team appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
Powers on an applicationE+W
3(1)On an application for a compulsory works order, the Minister or the Secretary of State may make the order either in the terms of the draft order submitted or, subject to sub-paragraphs (2) and (3) below, in those terms as modified in such manner as he thinks fit, or may refuse to make an order.E+W
(2)Neither of the Ministers shall make such a modification of a draft order as he considers is likely adversely to affect any persons unless he is satisfied that the [Agency] has given and published such additional notices, in such manner, as he may have required.
(3)Neither of the Ministers shall, unless all interested parties consent, make a compulsory works order so as to confer in relation to any land any powers of compulsory acquisition which would not have been conferred in relation to that land if the order were made in the terms of the draft order submitted under paragraph 1 above.
(4)Where one of the Ministers refuses, on an application for a compulsory works order, to make an order, the [Agency] shall, as soon as practicable after the refusal, notify the refusal to every person on whom it was, by virtue of paragraph 1(1)(c)(i) above, required to serve a copy of the notice with respect to the application.
Back to top