Modifications etc. (not altering text)
C1Pt. II: transfer of functions to the Environment Agency (1.4.1996) by 1995 c. 25, s. 2(1)(a)(i) (with ss. 115, 117); S.I. 1996/186, art. 3
Modifications etc. (not altering text)
C2Chapter II of Part II excluded (1.4.1996) by 1995 c. 25, s. 6(3) (with ss. 7(6), 115, 117); S.I. 1996/186, art. 3
C3Chapter II of Part II modified (18.12.1996) by 1996 c. 61, s. 52, Sch. 15 Pt. III para. 11
C4Pt. II Ch. II modified (22.3.2005) by Midland Metro (Wednesbury to Brierley Hill and Miscellaneous Amendments) Order 2005 (S.I. 2005/927), Sch. 11 para. 11 (with art. 51)
C5Pt. II Ch. II modified (26.8.2005) by River Tyne (Tunnels) Order 2005 (S.I. 2005/2222), art. 1, Sch. 10 para. 14 (with arts. 45(1), 48, Sch. 10 paras. 21, 29)
C6Pt. II Ch. II modified (19.3.2007) by Ouseburn Barrage Order 2007 (S.I. 2007/608), art. 1, Sch. 6 para. 18 (with arts. 46-48, Sch. 6 paras. 17(5), 23)
C7Pt. II Ch. II modified (22.7.2008) by Crossrail Act 2008 (c. 18), Sch. 17 para. 11
C8Pt. II Ch. II modified (9.6.2009) by Nottingham Express Transit System Order 2009 (S.I. 2009/1300), arts. 1, 71(12) (with Sch. 13 para. 14(2), Sch. 14 para. 19, Sch. 16)
C9Pt. II Ch. II modified (20.7.2010) by The Network Rail (Nuneaton North Chord) Order 2010 (S.I. 2010/1721), art. 1, Sch. 11 para. 12
C10Pt. II Ch. II modified (27.8.2010) by The Llangollen and Corwen Railway Order 2010 (S.I. 2010/2136), art. 1(1), Sch. 4 para. 12
C11Pt. II Ch. II modified (1.9.2010) by The Port of Bristol (Deep Sea Container Terminal) Harbour Revision Order 2010 (S.I. 2010/2020), art. 1(2), Sch. 6 para. 11(1) (with arts. 18, 19)
C12Pt. II Ch. II modified (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), art. 1, Sch. 10 para. 41(1) (with art. 51, Sch. 10 paras. 6885)
(1)Without prejudice to sections 38(3) and 39(1) above, subsection (2) or, as the case may be, subsection (3) below shall apply where any application for a licence under this Chapter relates to abstraction from any inland waters or to obstructing or impeding the flow of any inland waters by means of impounding works.
(2)If, in the case of such an application as is mentioned in subsection (1) above, the application is made at a time when no minimum acceptable flow for the inland waters in question has been determined under Chapter I of this Part, the [F1appropriate agency], in dealing with the application, shall have regard to the considerations by reference to which, in accordance with section 21(4) and (5) above, a minimum acceptable flow for those waters would fall to be determined.
(3)If, in the case of such an application as is mentioned in subsection (1) above, the application is made at a time after a minimum acceptable flow for the waters in question has been determined under Chapter I of this Part, the [F1appropriate agency], in dealing with the application, shall have regard to the need to secure or, as the case may be, secure in relation to the different times or periods for which the flow is determined—
(a)that the flow at any control point will not be reduced below the minimum acceptable flow at that point; or
(b)if it is already less than that minimum acceptable flow, that the flow at any control point will not be further reduced below the minimum acceptable flow at that point.
(4)Without prejudice to sections 38(3) and 39(1) above, where—
(a)an application for a licence under this Chapter relates to abstraction from underground strata; and
(b)it appears to the [F1appropriate agency] that the proposed abstraction is likely to affect the flow, level or volume of any inland waters which are neither discrete waters nor waters comprised in an order under section 33 above,
subsection (2) or, as the case may be, subsection (3) above shall apply as if the application related to abstraction from those waters.
Textual Amendments
F1Words in ss. 33A-45 substituted (1.4.2013) by The Natural Resources Body for Wales (Functions) Order 2013 (S.I. 2013/755), art. 1(2), Sch. 2 para. 270(g) (with Sch. 7)
Modifications etc. (not altering text)
C13S. 40(1) applied (1.4.2006) by Water Resources (Abstraction and Impounding) Regulations 2006 (S.I. 2006/641), reg. 1(2), Sch. 2 para. 8(5)