Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)Subject to subsection (7) below, where—
(a)a petition for the alteration of the boundaries of an internal drainage district is made to the [F1appropriate supervisory body] by a sufficient number of qualified persons or by a qualified authority; and
(b)the boundaries of that district have for a period exceeding ten years been neither reviewed on such a petition nor altered,
the [F1appropriate supervisory body] shall review those boundaries.
(2)Subject to subsection (7) below, where a petition under subsection (1) above is received by the [F1appropriate supervisory body] in the circumstances mentioned in subsection (1)(b) above, the [F1appropriate supervisory body] shall—
(a)inform the relevant Minister; and
(b)publishF2... a notice stating—
(i)that the petition has been received;
(ii)that a review of the boundaries is being undertaken; and
(iii)that representations may be made to the [F1appropriate supervisory body] within a period (which shall not be less than thirty days) stated in the notice.
F3(2A). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(3)In carrying out any review required by this section the [F1appropriate supervisory body] shall—
(a)consult the drainage board for the internal drainage district in question, unless it is itself the drainage board; and
(b)consider any representations duly made to it.
(4)Within six months after a petition under this section is made or such longer period as the relevant Minister may allow, the [F1appropriate supervisory body] shall inform the relevant Minister—
(a)whether, as a result of the review, it proposes to submit to him a scheme under section 3 below; and
(b)if so, what provision it proposes to make by the scheme.
(5)Subject to subsection (6) below, where—
(a)the [F1appropriate supervisory body] does not propose, as a result of the review, to submit to the relevant Minister a scheme under section 3 below; but
(b)it appears to the [F1appropriate supervisory body] that an order under section 38 below, or an order varying or revoking such an order, should be made by the drainage board for the internal drainage district in question,
the [F1appropriate supervisory body] may direct the drainage board to make such an order in such terms as may be specified in the direction.
(6)If an internal drainage board to which a direction has been given under subsection (5) above object to the direction, the direction shall have no effect unless it is confirmed (with or without modifications) by the relevant Minister.
(7)This section does not require the [F1appropriate supervisory body] to carry out a review or publish any notice on a petition which, in the opinion of the relevant Minister, is frivolous.
Textual Amendments
F1Words in s. 3 substituted (1.4.2013) by The Natural Resources Body for Wales (Functions) Order 2013 (No. 755), art. 1(2), Sch. 2 para. 317 (with Sch. 7)
F2Words in s. 2(2)(b) repealed (14.7.2014) by Water Act 2014 (c. 21), s. 94(3), Sch. 9 para. 2(2); S.I. 2014/1823, art. 2(b)
F3S. 2(2A) omitted (21.5.2016) by virtue of Environment (Wales) Act 2016 (anaw 3), ss. 82(1), 88(2)(d)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: