Competition and Service (Utilities) Act 1992

25Determination of disputes by Director: interim directions

(1)The power of the Director General of Electricity Supply, under section 23(2) of the [1989 c. 29.] Electricity Act 1989, to require a public electricity supplier to continue a supply of electricity pending the Director’s determination of a dispute shall be extended to enable the Director to require the giving of a supply of electricity pending such a determination.

(2)Accordingly, in section 23(2) of that Act, the words “to continue” shall be omitted, in both places where they occur.