Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
13(1)On being required under paragraph 12 above to carry out remedial work the Development Corporation shall—U.K.
(a)as soon as reasonably practicable, arrange for the execution of appropriate work at their expense,
(b)ensure that the work is commenced before the end of the period of six months beginning with the day on which they are so required, and
(c)be responsible for obtaining all necessary statutory consents and approvals in relation to the work.
(2)If the Development Corporation fail to comply with sub-paragraph (1)(b) above, the person who required them to carry out the work may nominate a contractor (with the contractor’s consent); and the Development Corporation shall make arrangements with the contractor for the execution of the work unless the Development Corporation—
(a)have reasonable grounds for refusing to do so, and
(b)within twenty-eight days of receiving the nomination of the contractor, give the reasons for their refusal to the person who made the nomination.
(3)Any dispute as to—
(a)whether the report of a survey of a building carried out under paragraph 4, 5 or 6 above shows that the building has suffered or is likely to suffer groundwater damage,
(b)whether the report of monitoring of a building carried out under paragraph 10 above recommends the carrying out of remedial work to the building,
(c)whether a requirement to carry out remedial work has been made to the Development Corporation,
(d)what constitutes appropriate work for the purposes of sub-paragraph (1) above, or
(e)whether the Development Corporation have reasonable grounds for refusing to make arrangements for the execution of work by a nominated contractor,
shall be determined in accordance with paragraph 25 below.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: