Print Options
PrintThe Whole
Act
PrintThe Whole
Schedule
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Paragraph 23
Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Version Superseded: 01/04/1996
Status:
Point in time view as at 05/11/1993. This version of this provision has been superseded.
Status
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Changes to legislation:
There are currently no known outstanding effects for the Cardiff Bay Barrage Act 1993, Paragraph 23.
Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
23(1)The status of any building as a building within the protected property area shall be a local land charge; and where—
(a)a direction is given by the Secretary of State under paragraph 2(2)(b) above affecting any building, or
(b)paragraph 9 above applies in the case of any building,
the Development Corporation shall notify the council of the district in which the building is situated of the fact that the building is, by virtue of that provision, to be regarded as being within the protected property area.
(2)If a survey of a building is carried out under paragraph 5(1) or (3) above, or if compensation in relation to a building is paid under paragraph 15 above, the Development Corporation shall deposit with the council of the district in which that building is situated particulars of the survey or compensation, and those particulars shall be a local land charge.
(3)For the purposes of the Local Land Charges Act 1975 the council of the district shall be treated as the originating authority as respects any charge constituted by virtue of this paragraph.