Railways Act 1993

Review implementation noticeE+W+S

7(1)After a copy of a notice of agreement is served on the beneficiary and the time within which a termination notice may be given by him has expired—

(a)if he has not given a termination notice (or has withdrawn any notice which he has given), the Regulator shall (unless he acts under paragraph 8(2) below) give a review implementation notice; or

(b)if he has given (and not withdrawn) a termination notice, the Regulator may give such a notice.

(2)A review implementation notice is a notice stating that the Regulator’s conclusions on the access charges review are to be implemented as proposed in the review notice.

(3)The review implementation notice shall—

(a)specify the relevant changes which the Regulator is making; and

(b)state, in relation to each of the relevant changes, the date on which it comes into operation.

(4)The review implementation notice shall be given—

(a)by publishing it in such manner as the Regulator considers appropriate for the purpose of bringing it to the attention of persons likely to be affected by the relevant changes; and

(b)by serving a copy on the persons on whom a copy of the review notice was served, the Authority and the Health and Safety Executive.