SCHEDULE 4A Review of access charges by the Office of Rail Regulation
Review implementation notice
7
(1)
After a copy of a notice of agreement is served on the beneficiary and the time within which a termination notice may be given by him has expired—
(a)
(b)
if he has given (and not withdrawn) a termination notice, F1the Office of Rail Regulation may give such a notice.
(2)
A review implementation notice is a notice stating that F1the Office of Rail Regulation’s conclusions on the access charges review are to be implemented as proposed in the review notice.
(3)
The review implementation notice shall—
(a)
specify the relevant changes which F1the Office of Rail Regulation is making; and
(b)
state, in relation to each of the relevant changes, the date on which it comes into operation.
(4)
The review implementation notice shall be given—
(a)
by publishing it in such manner as F1the Office of Rail Regulation considers appropriate for the purpose of bringing it to the attention of persons likely to be affected by the relevant changes; and
(b)
by serving a copy on the persons on whom a copy of the review notice was served, F3. . . .