Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)Subject to subsections (2) and (5) and section 32 below, where the Authority is satisfied—
(a)that any person is carrying on any coal-mining operations in contravention of section 25(1) above, or is likely so to carry on any coal-mining operations, or
(b)that any person is contravening, or is likely to contravene, any of the conditions of a licence under this Part,
the Authority may, by a final enforcement order, make such provision in relation to that person as is requisite for the purpose of securing that there is no contravention of section 25(1) above or, as the case may be, that that condition is complied with.
(2)Subject to subsection (5) below, where—
(a)it appears to the Authority as mentioned in subsection (1)(a) or (b) above, and
(b)it appears to the Authority that it is appropriate that a provisional enforcement order be made,
the Authority may (instead of taking steps towards the making of a final enforcement order) by a provisional enforcement order make such provision in relation to the person in question as appears to it requisite for the purpose of securing that there is no contravention of section 25(1) above or, as the case may be, that the condition is complied with.
(3)In determining for the purposes of subsection (2)(b) above whether it is appropriate that a provisional enforcement order be made, the Authority shall have regard, in particular, to the extent to which any person is likely to sustain loss or damage in consequence of anything which, in contravention of section 25(1) above or the condition in question, is likely to be done, or omitted to be done, before a final enforcement order may be made.
(4)Subject to subsection (5) and section 32 below, where a provisional enforcement order has been made, the Authority shall consider whether, for the purpose of giving it final effect, it should be confirmed and shall be entitled to confirm it, with or without modifications, if—
(a)it is satisfied that the person to whom the order relates—
(i)is carrying on any coal-mining operations in contravention of section 25(1) above, or is likely so to carry on any coal-mining operations; or
(ii)is contravening, or is likely to contravene, any of the conditions of a licence under this Part;
and
(b)the provision made by the order (with any modifications) is requisite for the purpose of securing that there is no contravention of section 25(1) above or, as the case may be, that that condition is complied with.
(5)The Authority shall not make a final enforcement order or make or confirm a provisional enforcement order in relation to any person if it is satisfied—
(a)that that person has agreed to take, and is taking, all such steps as it appears to the Authority for the time being to be appropriate for him to take for the purpose of securing that there is no contravention of section 25(1) above or that the condition in question is complied with; or
(b)that the contraventions of section 25(1) above or of that condition were, or the apprehended contraventions are, of a trivial nature.
(6)An enforcement order—
(a)shall require the person to whom it relates (according to the circumstances of the case) to do, or not to do, such things as are specified in the order or are of a description so specified;
(b)shall take effect at such time, being the earliest practicable time, as is determined by or under the order; and
(c)may be revoked at any time by the Authority.
(7)In this Part—
“enforcement order” means a final enforcement order or a provisional enforcement order;
“final enforcement order” means an order under this section other than a provisional enforcement order; and
“provisional enforcement order” means an order under this section which, if not previously confirmed under subsection (4) above, will cease to have effect at the end of such period (not exceeding three months) as is determined by or under the order.
(8)This section and sections 32 and 33 below shall be without prejudice to the right of the Authority, where the conditions of any licence under this Part contain provision for a sum determined by or under those conditions to be paid to the Authority, to enforce that condition in proceedings for the recovery of the sum as an amount due to the Authority by virtue of an enactment.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: