Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
(1)This section has effect—
(a)for the purposes of section 37(1) below, as it applies in relation to the Agency; F2...
[F3(aa)for the purposes of article 9 of the Natural Resources Body for Wales (Establishment) Order 2012 (S.I.2012/1903), in relation to the Natural Resources Body for Wales; and]
(b)for the construction of any other enactment which, by reference to the functions of [F4an appropriate agency], confers any power on or in relation to [F4an appropriate agency];
and any reference in this section to “the relevant purposes” is a reference to the purposes described in paragraphs (a) [F5, (aa)] and (b) above.
(2)For the relevant purposes, the functions of [F6an appropriate agency] shall be taken to include the protection against pollution of—
(a)any waters, whether on the surface or underground, which belong to the [F7appropriate agency] or any water undertaker or from which the [F7appropriate agency] or any water undertaker is authorised to take water;
(b)without prejudice to paragraph (a) above, any reservoir which belongs to or is operated by the [F7appropriate agency] or any water undertaker or which the [F7appropriate agency] or any water undertaker is proposing to acquire or construct for the purpose of being so operated; and
(c)any underground strata from which the [F7appropriate agency] or any water undertaker is for the time being authorised to abstract water in pursuance of a licence under Chapter II of Part II of the 1991 Act (abstraction and impounding).
(3)For the relevant purposes, the functions of [F8an appropriate agency] shall be taken to include joining with or acting on behalf of one or more relevant undertakers for the purpose of carrying out any works or acquiring any land which at least one of the undertakers with which it joins, or on whose behalf it acts, is authorised to carry out or acquire for the purposes of—
(a)any function of that undertaker under any enactment; or
(b)any function which is taken to be a function of that undertaker for the purposes to which section 217 of the M1Water Industry Act 1991 applies.
(4)For the relevant purposes, the functions of [F9an appropriate agency] shall be taken to include the provision of supplies of water in bulk, whether or not such supplies are provided for the purposes of, or in connection with, the carrying out of any other function of the [F10appropriate agency] .
(5)For the relevant purposes, the functions of [F11an appropriate agency] shall be taken to include the provision of houses and other buildings for the use of persons employed by the [F12appropriate agency] and the provision of recreation grounds for persons so employed.
(6)In this section—
“relevant undertaker” means a water undertaker or sewerage undertaker; and
“supply of water in bulk” means a supply of water for distribution by a water undertaker taking the supply.
Textual Amendments
F1Words in s. 10 heading inserted (1.4.2013) by The Natural Resources Body for Wales (Functions) Order 2013 (S.I. 2013/755), art. 1(2), Sch. 2 para. 369(6) (with Sch. 7)
F2Word in s. 10(1)(a) omitted (1.4.2013) by virtue of The Natural Resources Body for Wales (Functions) Order 2013 (S.I. 2013/755), art. 1(2), Sch. 2 para. 369(2)(a) (with Sch. 7)
F3S. 10(1)(aa) inserted (1.4.2013) by The Natural Resources Body for Wales (Functions) Order 2013 (S.I. 2013/755), art. 1(2), Sch. 2 para. 369(2)(b) (with Sch. 7)
F4Words in s. 10(1)(b) substituted (1.4.2013) by The Natural Resources Body for Wales (Functions) Order 2013 (S.I. 2013/755), art. 1(2), Sch. 2 para. 369(2)(c) (with Sch. 7)
F5Word in s. 10(1)(b) inserted (1.4.2013) by The Natural Resources Body for Wales (Functions) Order 2013 (S.I. 2013/755), art. 1(2), Sch. 2 para. 369(2)(d) (with Sch. 7)
F6Words in s. 10(2) substituted (1.4.2013) by The Natural Resources Body for Wales (Functions) Order 2013 (S.I. 2013/755), art. 1(2), Sch. 2 para. 369(3)(a) (with Sch. 7)
F7Words in s. 10(2)(a)-(c) substituted (1.4.2013) by The Natural Resources Body for Wales (Functions) Order 2013 (S.I. 2013/755), art. 1(2), Sch. 2 para. 369(3)(b) (with Sch. 7)
F8Words in s. 10(3) substituted (1.4.2013) by The Natural Resources Body for Wales (Functions) Order 2013 (S.I. 2013/755), art. 1(2), Sch. 2 para. 369(4) (with Sch. 7)
F9Words in s. 10(4) substituted (1.4.2013) by The Natural Resources Body for Wales (Functions) Order 2013 (S.I. 2013/755), art. 1(2), Sch. 2 para. 369(5)(a) (with Sch. 7)
F10Words in s. 10(4) substituted (1.4.2013) by The Natural Resources Body for Wales (Functions) Order 2013 (S.I. 2013/755), art. 1(2), Sch. 2 para. 369(5)(b) (with Sch. 7)
F11Words in s. 10(5) substituted (1.4.2013) by The Natural Resources Body for Wales (Functions) Order 2013 (S.I. 2013/755), art. 1(2), Sch. 2 para. 369(5)(a) (with Sch. 7)
F12Words in s. 10(5) substituted (1.4.2013) by The Natural Resources Body for Wales (Functions) Order 2013 (S.I. 2013/755), art. 1(2), Sch. 2 para. 369(5)(b) (with Sch. 7)
Marginal Citations
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: