xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

MiscellaneousU.K.

12 Acquisition of rights to use gas processing facilities[F1 for downstream purposes].E+W+S

[F2(1)The owner of a gas processing facility [F3which processes gas for a downstream purpose]

(a)shall publish at least once in every year the main commercial conditions relating to the grant to another person of a right to have gas processed by the facility [F4for such a purpose]; and

(b)shall publish any changes to the published conditions as soon as they become effective.

[F5(1ZA)At least two months before publishing those conditions or any changes to them under subsection (1), the owner of the facility must—

(a)publish a draft of the proposed conditions or changes; and

(b)inform any person who has a right to have gas processed by the facility that the draft has been published.

(1ZB)The owner of the facility must take into account any representations received about the proposed conditions or changes before publishing them, or a modified version of them, as final conditions or changes under subsection (1).]

(1A)In subsection (1) “year” means any year ending with 9th August.

(1B)Any person who seeks a right to have gas processed [F6for a downstream purpose] by a gas processing facility (“the applicant”) shall, before making an application to [F7the Authority] under subsection (1F), apply to the owner of the facility for the right.

(1C)An application under subsection (1B) shall be made by giving notice in writing to the owner specifying what is being sought.

(1D)The notice shall, in particular, specify—

(a)the period during which the gas is to be processed by the facility;

(b) the kind of gas to be processed (which must be of, or similar to, the kind which the facility is designed to process); F8...

(c)the quantities of gas to be processed[F9; and

(d)that the gas is to be processed for a downstream purpose]

(1E)Where a person gives notice under subsection (1C), he and the owner of the gas processing facility shall negotiate in good faith and endeavour to reach agreement on the application.

(1F)If the owner and the applicant do not reach any such agreement, the applicant may apply to [F7the Authority] for directions under this section which would secure to the applicant the right specified in the notice under subsection (1C).

(1G)[F7the Authority] shall not entertain such an application unless [F10it] is satisfied that the parties have had a reasonable time in which to fulfil their duties under subsection (1E).]

(2)Where an application is made under [F11subsection (1F)], it shall be the duty of [F7the Authority]

(a)to decide whether the application is to be adjourned (so as to enable F12... further negotiations to take place), considered further or rejected;

(b)to give notice of [F13its] decision to the applicant; and

(c)in the case of a decision that the application is to be considered further, to give to the owner of the facility, to any person who has a right to have gas processed by the facility, and to the Health and Safety Executive, notice that the application is to be so considered and an opportunity of being heard about the matter.

(3)Where, after further considering an application under [F14subsection (1F)], [F7the Authority] is satisfied that the giving of directions under this section would not prejudice the efficient operation of the facility, or the processing by the facility of—

(a)the quantities of gas which the owner of the facility or any associate of the owner requires or may reasonably be expected to require to be processed by the facility for the purposes of any business carried on by him; and

(b)the quantities of gas which any person who is not such an associate and has a right to have gas processed by the facility is entitled to require to be so processed in the exercise of that right,

[F7the Authority] may give such directions to the owner of the facility.

(4)Directions under this section may—

(a)specify the terms on which [F7the Authority] considers the owner of the facility should enter into an agreement with the applicant for all or any of the following purposes—

(i)for securing to the applicant the right to have processed by the facility, during the period specified in the directions and in the quantities so specified, gas which is of a kind so specified;

(ii)for securing that the exercise of that right is not prevented or impeded;

(iii)for regulating the charges which may be made for the processing of gas by virtue of that right;

(iv)for securing to the applicant such ancillary or incidental rights as [F7the Authority] considers necessary or expedient, which may include the right to have a pipe-line of his connected to the facility by the owner;

(b)specify the sums or the method of determining the sums which [F7the Authority] considers should be paid by way of consideration for any such right; and

(c)require the owner, if the applicant pays or agrees to pay those sums within a period specified in that behalf in the directions, to enter into an agreement with him on the terms so specified.

[F15(5) Sections 28 to 30F of the 1986 Act (enforcement of relevant requirements etc) apply in relation to the owner of a gas processing facility as if—

(a)references to “a licence holder” were references to the owner of the facility; and

(b)references to a “relevant requirement” were references to a requirement imposed on the owner under this section.

(5A)For the purposes of this section, gas is processed for “a downstream purpose” if it is processed with a view to its being put into a gas storage facility, an LNG import or export facility, a gas interconnector or a distribution system pipeline.]

(6)In this section—

[F21(6A)Subsections (1) to (3) of section 49 of the Pipe-lines Act 1962 (service of documents) shall apply for the purposes of this section as they apply for the purposes of that Act.]

[F22(7)Section 91 of the Energy Act 2011 (meaning of “associate”) applies for the purposes of subsection (3) of this section as it applies for the purposes of section 82(7)(d) and (9)(a) of that Act.]

(8)In relation to any time before the appointed day, this section shall have effect as if for the words “public gas transporter”, in each place where they occur, there were substituted the words “public gas supplier”.

Textual Amendments

F1 Words in s. 12 heading inserted (21.3.2012) by Energy Act 2011 (c. 16), ss. 92(2), 121(1); S.I. 2012/873, art. 2(b)(ii) (with art. 4)

F2 S. 12(1)-(1G) substituted (10.8.2000) for s. 12(1) by S.I. 2000/1937, reg. 2(3), Sch. 3 para. 1

F3 Words in s. 12(1) inserted (21.3.2012) by Energy Act 2011 (c. 16), ss. 92(4)(a), 121(1); S.I. 2012/873, art. 2(b)(ii) (with art. 4)

F4 Words in s. 12(1)(a) substituted (21.3.2012) by Energy Act 2011 (c. 16), ss. 92(4)(b), 121(1); S.I. 2012/873, art. 2(b)(ii) (with art. 4)

F5 S. 12(1ZA)(1ZB) inserted (21.3.2012) by Energy Act 2011 (c. 16), ss. 92(5), 121(1); S.I. 2012/873, art. 2(b)(ii) (with art. 4)

F6 Words in s. 12(1B) substituted (21.3.2012) by Energy Act 2011 (c. 16), ss. 92(6), 121(1) ; S.I. 2012/873, art. 2(b)(ii) (with art. 4)

F7 Words in s. 12 substituted (21.3.2012) by Energy Act 2011 (c. 16), ss. 92(3), 121(1); S.I. 2012/873, art. 2(b)(ii) (with art. 4)

F8 Word in s. 12(1D) omitted (21.3.2012) by virtue of Energy Act 2011 (c. 16), ss. 92(7)(a), 121(1); S.I. 2012/873, art. 2(b)(ii) (with art. 4)

F9 S. 12(1D)(d) and preceding word inserted (21.3.2012) by Energy Act 2011 (c. 16), ss. 92(7)(b), 121(1); S.I. 2012/873, art. 2(b)(ii) (with art. 4)

F10 Word in s. 12(1G) substituted (21.3.2012) by Energy Act 2011 (c. 16), ss. 92(8) , 121(1); S.I. 2012/873, art. 2(b)(ii) (with art. 4)

F11 Words in s. 12(2) substituted (10.8.2000) by S.I. 2000/1937, reg. 2(3), Sch. 3 para. 2(a)

F12 Words in s. 12(2)(a) repealed (10.8.2000) by S.I. 2000/1937, reg. 2(3), Sch. 3 para. 2(b)

F13 Word in s. 12(2)(b) substituted (21.3.2012) by Energy Act 2011 (c. 16), ss. 92(9), 121(1); S.I. 2012/873, art. 2(b)(ii) (with art. 4)

F14 Words in s. 12(3) substituted (10.8.2000) by S.I. 2000/1937, reg. 2(3), Sch. 3 para. 3

F15 S. 12(5)(5A) substituted (21.3.2012) by Energy Act 2011 (c. 16), ss. 92(10), 121(1); S.I. 2012/873, art. 2(b)(ii) (with art. 4)

F16 Words in s. 12(6) inserted (21.3.2012) by Energy Act 2011 (c. 16) , ss. 92(11)(b), 121(1); S.I. 2012/873, art. 2(b)(ii) (with art. 4)

F17 Words in s. 12(6) substituted (21.3.2012) by Energy Act 2011 (c. 16), ss. 92(11)(a), 121(1); S.I. 2012/873, art. 2(b)(ii) (with art. 4)

F19 Words in s. 12(6) inserted (6.4.2009) by Energy Act 2008 (c. 32), ss. 78(2)(a), 110(2); S.I. 2009/45, art. 4(c)

F20 Definition of “main commercial conditions” in s. 12(6) inserted (10.8.2000) by S.I. 2000/1937, reg. 2(3), Sch. 3 para. 5(b)

F21 S. 12(6A) inserted (10.8.2000) by S.I. 2000/1937, reg. 2(3), Sch. 3 para. 6

F22 S. 12(7) substituted (21.3.2012) by Energy Act 2011 (c. 16), ss. 92(12), 121(1); S.I. 2012/873, art. 2(b)(ii) (with art. 4)

Marginal Citations