- Latest available (Revised)
- Original (As enacted)
There are currently no known outstanding effects for the Channel Tunnel Rail Link Act 1996, Cross Heading: Trees.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
(1)Where any tree overhangs land used for the purposes of the nominated undertaker’s undertaking under this Part of this Act, the nominated undertaker may by notice to the occupier of the land on which the tree is growing require the tree to be removed, topped or lopped if it is necessary for that to be done—
(a)to enable the works authorised by this Part of this Act to be maintained, or
(b)for reasons of safety in connection with the operation of any railway comprised in those works.
(2)If, within the period of 28 days beginning with the giving by the nominated undertaker of a notice under subsection (1) above, the occupier of the land on which the tree to which the notice relates is growing gives the nominated undertaker a counter-notice objecting to the removal, topping or lopping of the tree, the notice shall have effect only if confirmed by an order of the county court.
(3)If at any time a notice under subsection (1) above has not been complied with and either—
(a)a period of 28 days beginning with the giving of the notice has expired without a counter-notice having been given, or
(b)an order of the court confirming the notice has come into force,
the nominated undertaker may itself cause the tree to which the notice relates to be removed, topped or lopped as mentioned in subsection (1) above.
(4)Where the power conferred by subsection (3) above is exercisable in relation to any tree, the nominated undertaker may—
(a)enter the land on which the tree is growing for the purpose of exercising that power in relation to it, and
(b)take with it such vehicles and equipment as are necessary for that purpose.
(5)Where the nominated undertaker tops or lops a tree in exercise of the power conferred by subsection (3) above, it shall do so in a husband-like manner and in such a way as to cause the minimum of damage to the tree.
(6)Where—
(a)a notice under subsection (1) above is complied with either without a counter-notice having been given or after the notice has been confirmed, or
(b)the nominated undertaker exercises the power conferred by subsection (3) above,
the county court shall, on application made by a person who has suffered loss or damage in consequence of the removal, topping or lopping of the tree concerned or who has incurred expenses in complying with the notice, order the nominated undertaker to pay that person such compensation in respect of the loss, damage or expenses as it thinks fit.
Modifications etc. (not altering text)
C1S. 27 applied (with modifications) (19.2.1999) by S.I. 1999/537, art. 13(1), Sch. 3 paras. 1-8
S. 27 applied (with modifications) (22.3.2001) by S.I. 2001/1451, art. 15(1), Sch. 3 para. 1(a)
(1)The following, namely—
(a)an order under section 198(1) of the M1Town and Country Planning Act 1990 (tree preservation orders), and
(b)section 211(1) of that Act (which prohibits the doing in a conservation area of any act which might be prohibited by a tree preservation order),
shall not apply to any tree works which are authorised for the purposes of this section.
(2)Tree works are authorised for the purposes of this section if—
(a)they are carried out in compliance with a notice under subsection (1) of section 27 above or in exercise of the power conferred by subsection (3) of that section,
(b)they are carried out in relation to a tree growing on land within the relevant limits and for the purposes of or in connection with the construction of the works authorised by this Part of this Act, or
(c)they are carried out in relation to a tree growing on land used for the purpose of the nominated undertaker’s undertaking under this Part of this Act and in circumstances where it is necessary for them to be carried out—
(i)to enable the works authorised by this Part of this Act to be maintained, or
(ii)for reasons of safety in connection with the operation of any railway comprised in those works.
(3)In subsection (2)(b) above, the reference to land within the relevant limits is to land within the limits of deviation for the scheduled works or within the limits of land to be acquired or used.
(4)In this section, references to tree works are to works consisting of the removal, topping or lopping of a tree.
Modifications etc. (not altering text)
C2S. 28 applied (with modifications) (19.2.1999) by S.I. 1999/537, art. 13(1), Sch. 3 paras. 1-8
S. 28 applied (with modifications) (22.3.2001) by S.I. 2001/1451, art. 15(1), Sch. 3 para. 1(a)
Marginal Citations
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: