3(1)Before beginning to construct any specified work, the nominated undertaker shall submit to [F1Canal & River Trust] plans of the work and such further particulars available to it as [F1Canal & River Trust] may within 14 days of the submission of the plans reasonably require.U.K.

(2)Any specified work shall not be constructed except in accordance with such plans as may be approved in writing by [F1Canal & River Trust] or determined under paragraph 11 below.

(3)Any approval of [F1Canal & River Trust] required under this paragraph shall not be unreasonably withheld and—

(a)shall be deemed to have been given if it is neither given nor refused within 28 days of the submission of the plans for approval; and

(b)may be given subject to such reasonable requirements as [F1Canal & River Trust] may make for the purpose of ensuring the safety or stability of the canal, including requirements as to the construction of protective works.