Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
1(1)Subject to the provisions of this paragraph, the nominated undertaker may, in connection with the construction of the works authorised by this Part of this Act, stop up each of the highways or parts of highways specified, by reference to the letters and numbers shown on the deposited plans, in columns (1) and (2) of the following table.U.K.
(2)No highway or part of a highway specified in columns (1) and (2) of Part I of the following table shall be stopped up under this paragraph unless all the land which abuts on it falls within one or more of the following categories, namely—
(a)land to which there is no right of access directly from the highway or part to be stopped up,
(b)land to which there is reasonably convenient access otherwise than directly from the highway or part to be stopped up,
(c)land the owners and occupiers of which have agreed to the stopping up of the highway or part, and
(d)land which is in the possession of the Secretary of State.
(3)No highway or part of a highway specified in columns (1) and (2) of Part II of the following table shall be stopped up under this paragraph if a new highway is specified in relation to it in column (3) of that Part of the table, by reference to the letters and numbers shown on the deposited plans or by reference to scheduled works, until—
(a)where the new highway is provided in exercise of the powers conferred by this Part of this Act, the later of the date of practical completion and the date on which it is first open for public use, and
(b)where it is not, the date on which it is first open for public use.
(4)Where a new highway specified in column (3) of Part II of the following table is provided in exercise of the powers conferred by this Part of this Act, the date of practical completion of the highway, or the date on which it is first open for public use, shall be taken for the purposes of sub-paragraph (3) above to be what it is taken to be for the purposes of paragraph 11(2) below.
(1) | (2) |
---|---|
Area | Highway or part to be stopped up |
GREATER LONDON | |
London Borough of Camden | Battlebridge Road between points E3 and E4 Wellers Court between points F1 and F2 Clarence Passage between points G1 and G2 Stanley Passage between points H1 and H2 |
London Borough of Barking and Dagenham | Footpath 47 between points M4 and M5 |
COUNTY OF ESSEX | |
Borough of Thurrock | Oliver Close between points F4 and F5 |
COUNTY OF KENT | |
Borough of Dartford, Parishes of Swanscombe and Greenhithe and Southfleet | Access road adjoining A2 between points D6, D7 and D8 |
Borough of Gravesham, Town of Gravesend | Footpath NU15 between points D3 and D4 |
Borough of Gravesham, Parish of Cobham | Old Watling Street (B395) between points K1 and K2 |
City of Rochester upon Medway, Parish of Cuxton | Footpath RS 205 between points D1 and D2 Footpath RR 27 between points D2 and D3 |
Borough of Maidstone, Parish of Hollingbourne | Musket Lane between points A4 and A3 |
Borough of Maidstone, Parish of Harrietsham | Footpath KH275 between points E5 and E3 |
Borough of Ashford, Parish of Charing | Footpath AW47 between points K1 and K2 |
Borough of Ashford, Town of Ashford | Gasworks Lane (D4543) between points E1 and E2 |
Borough of Ashford, Parish of Mersham | Footpath AE 386 between points C10 and C11 |
Borough of Ashford, Parish of Smeeth | Footpath AE 434 between points C3 and C2 |
District of Shepway, Parishes of Saltwood and Stanford | Footpath HE 346 between points A2 and A5 Stone Street between points B1 and B2 |
District of Shepway, Parish of Saltwood | Footpath HE 279 between points C9 and C10 Sandy Lane (D1752) between points C11 and C8 |
(1) | (2) | (3) |
---|---|---|
Area | Highway or part to be stopped up | New highway to be substituted for it |
GREATER LONDON | ||
London Borough of Camden | Midland Road between points B1 and B2 | Work No. 5B |
Pancras Road between points C1, B2 and C2 | Works Nos. 5B, 5C and 5D | |
Taxi Road between points D1, D2 and D3 | Works Nos. 5F and 5F(1) | |
Cheney Road between points E1, E2 and E3 | Work No. 5C | |
Goods Way between points K1 and K5 | Work No. 5D | |
Camley Street between points K4 and K6 | Works Nos. 5A and 5C | |
York Way between points L1 and L2 | Work No. 5Q | |
London Borough of Islington | Randell’s Road between points A1 and A2 | Work No. 5Q(1) |
London Borough of Barking and Dagenham | Pooles Lane between points M1 and M2 | Work No. 22H(1) between its commencement and its junction with Work No. 22H(2), and Work No. 22H(2) |
Choats Manor Way between points M3 and M4 | Work No. 22H(1) between its commencement and its junction with Work No. 8P(3) | |
Choats Road between points L1 and L2 | Work No. 8P(3) | |
Hindmans Way between points L2 and L3 | Work No. 8P(3) | |
Chequers Lane between points L4 and L5 | Works Nos. 8P(3) and 8P(4) | |
Kent Avenue between points J1 and J2 | Work No. 8Q | |
Thames Avenue between points K1 and K2 | Work No. 8R | |
London Borough of Havering | Creekside between points C1 and C2 | Works Nos. 8S and 8T |
Lamson Road between points D1 and D3 | Work No. 8S | |
COUNTY OF ESSEX | ||
Borough of Thurrock | Footpath FP145 between points L1 and L2 | New footpath between points L1, L3, L4, L5, L6, L7 and L2 |
Arterial Road, Purfleet between points M1 and M2 | Work No. 23C(1) | |
Purfleet Bypass between points M3 and M4 | Work No. 23C(3) | |
Tank Lane between points M5 and M6 | Work No. 23C(5) and Work No. 23C(4) between point M5 and its termination | |
Botany Way between points M8 and M9 | Works Nos. 23C(2), 23C(3) and 23C(5) | |
Footpath 167 between points N1 and N2 | New footpath between points N1, N3 and N2 | |
Oliver Close (North) between points F1, F2 and F3 | Work No. 9B | |
Oliver Road between points G1 and G2 | Work No. 9C | |
Burnley Road and Watson Close between points H1, H2 and H3 | Work No. 9D | |
A1090 (Tank Hill Road) between points J8 and J2 | Work No. 23B(1) and new footpath between points J8 and J9 | |
Access road to Purfleet Industrial Park between points J5 and J6 | Work No. 23B(1) between its commencement and its junction with Work No. 23B(2), and Work No. 23B(2) | |
COUNTY OF KENT | ||
Borough of Dartford, Parish of Swanscombe and Greenhithe | Green Manor Way between points B1 and B2 | Works Nos. 10J and 10J(1) |
Footpath DS17 between points D1 and D2 | New footpath between points D1, D3 and D2 | |
Borough of Dartford, Parish of Swanscombe and Greenhithe and Borough of Gravesham, Town of Gravesend | Lower Road between points B3 and B4 | Work No. 10J |
Borough of Dartford, Parishes of Swanscombe and Greenhithe and Southfleet | Park Corner Road and Southfleet Road (B259) between points E1, E2 and E3 | Works Nos. 10S(2) and 10(T)(6) to 10T(8) |
Access road between points F1 and F2 | Works Nos. 10S(2), 10T(1), 10T(4), 10T(6) and 10T(8) | |
Borough of Dartford, Parish of Southfleet | Slip road from A2 to Park Corner Road between points C1 and C2 | Work No. 10T(8) |
Footpath DR132 between points B1 and B2 | New footpath between points B2 and B3 | |
New Barn Road between points A1 and A2 | Work No. 11F | |
Hook Green Road between points D1 and D2 | Work No. 11D | |
Borough of Dartford, Parishes of Longfield and New Barn and Southfleet | Whitehill Road between points A1 and A2 | Work No. 11C |
Borough of Dartford, Parish of Longfield and New Barn and District of Sevenoaks, Parish of Horton Kirby and South Darenth | Footpath DR160 between points B1 and B2 | New footpath between points B1, B3, B4 and B2 |
Borough of Gravesham, Town of Gravesend | Manor Way between points B5 and B6 | Work No. 10J(2) |
Footpath NU14 between points A1 and A2 | New footpath between points A1, A3, A4 and A2 | |
Footpath NU 7A between points B1 and B2 | New footpath between points B1, B3 and B2 | |
Footpath NU14 between points C1 and C2 | New footpath between points C1, C3 and C2 | |
Footpath NU16 between points D1 and D2 | New footpath between points D1 and D5 | |
Bridleway NU24 between points F1 and F2 | New bridleway between points F1, F5, F6 and F2 | |
Footpath NU23 between points F3 and F4 | New footpath between points F4 and F2 | |
Downs Road between points G1 and G2 | Work No. 10P | |
Access road to Hazells between points H1 and H2 | Work No. 10Q | |
Bridleway NU27 between points J1 and J2 | New bridleway between points J1, J3, J4 and J2 | |
Footpath NU29 between points L1 and L2 | New footpath between points L1, K3, L3 and L2 | |
Footpath NU9 between points K1 and K2 | New footpath between points K1 and K3 | |
Borough of Gravesham, Town of Gravesend and Parish of Cobham | Footpaths NU18, NS193 and NG15 between points M1 and M4 | New footpath between points M4 and M5 |
Borough of Gravesham, Parish of Cobham | Church Road between points A1 and A2 | Work No. 12C and new footpath between points A3, A4, A5 and A2 |
Footpaths NG16 and NS175 between points B1 and B3 | Works Nos. 12C and 12D and new footpath between points B3 and B4 | |
Henhurst Road between points C1 and C2 | Work No. 12D | |
Footpath NS177 between points D1 and D2 | Work No.12D and new footpaths between points D1 and D3 and between points D4 and D2 | |
Access road between points E1, E4 and E2 | New access roads between points E1, E3 and E2 and between points E3 and E4 | |
Scotland Lane (Byway NS195) between points F1 and F2 | Works Nos. 12E and 12F | |
Watling Street (B395) between points G1 and G2 | Work No. 12F | |
Access road between points F3 and F4 | Works Nos. 12E and 12F | |
Halfpence Lane (C492) and slip road to A2 between points H1 and H3 | Works Nos. 32B and 32C | |
Slip road from A2 to Halfpence Lane between points H4 and H2 | Work No. 32B | |
Footpath NS179 between points L1 and L2 | New footpaths between points L3 and L4 and between points L2 and L5 | |
Access road between points M1 and M2 | Work No. 12L | |
Borough of Gravesham, Parish of Shorne | A2 eastbound slip road between points J3 and J4 | Work No. 32A |
Borough of Gravesham, Parishes of Cobham and Shorne | Brewers Road between points J1 and J2 | Work No. 12H |
Access road between points K3 and K2 | Work No. 12K | |
Footpath NS180 between points K2 and K4 | Work No. 12K | |
Footpath NS161 between points K6, K2, K8 and K5 | Work No. 12K and new footpath between points L5, K7 and K5 | |
City of Rochester upon Medway, Town of Rochester and Parish of Cuxton | Footpath RS203 between points B2 and B3 | New footpath between points B2, B5, B4 and B3 |
A228 (Rochester Road) between points C1 and C3 | Work No. 13A(4) and Work No. 36F between its commencement and its junction with Work No. 13A(4) | |
M2 westbound entry slip road between points C6 and C7 | Work No. 13A(2), Work No. 36C between its junction with Work No. 13A(2) and its termination, and Work No. 36E between its junction with Work No. 36C and its termination | |
M2 westbound exit slip road between points C8 and C7 | Work No. 13A(3) and Work No. 36E between its junction with Work No. 36C and its termination | |
M2 eastbound exit slip road between points C9 and C4 | Works Nos. 13A(1) and 13A(4) and Work No. 36F between its commencement and its junction with Work No. 13A(4) | |
City of Rochester upon Medway, Town of Rochester | Burham Road (D422) between points A1 and A2 | Work No. 13B |
Bridleway RR16 between points E4, E11 and E12 | Work No. 13C between its junction with Work No. 38F and its termination, Work No. 38F between point E13 and its termination, and new bridleway between points E4 and E13 (having a junction at point E4 with bridleway RR16 as existing, so far as not stopped up under paragraph 3 of Schedule 12 below, or, if so stopped up, with Work No. 38C) | |
City of Rochester upon Medway, Town of Rochester and Borough of Tonbridge and Malling, Parish of Wouldham | Bridleway MR11 (Stony Lane) between points A1 and A2 | Work No. 13C |
Bridleway MR12 between points E12 and A1 | Work No. 13C | |
Borough of Tonbridge and Malling, Parish of Aylesford | Byway MR401 between points T1 and T2 | Work No. 13E |
Borough of Maidstone, Parish of Boxley | Boarley Lane (D898) between points A1 and A2 | Work No. 13G |
Footpath KH25 between points B1 and B2 | New footpath between points B1, B3 and B2 | |
Boxley Road (C97) between points C1 and C2 | Work No. 13H | |
Footpath KH15 between points D1 and D2 | New footpath between points D1, D3 and D2 | |
Borough of Maidstone, Parish of Thurnham | Footpath KH71 between points A1, A2 and A3 | New footpath between points A1, A4, A5 and A6 |
Thurnham Lane between points B1 and B2 | Work No. 14A | |
Bridleway KH123 between points C1, C2 and C3 | New bridleway between points C1 and C4 | |
Water Lane between points D1 and D2 | Work No. 14B | |
Footpath KH130 between points E1, E4 and E2 | New footpaths between points E1, E3 and E2 and between points E3 and E4 | |
Bridleway KH134 (Crismill Lane) between points F1 and F2 | Work No. 14C | |
Borough of Maidstone, Parishes of Thurnham and Hollingbourne | Footpath KH141 between points G1 and G2 | Work No. 14C and new footpath between points G3 and G2 |
Borough of Maidstone, Parish of Hollingbourne | Footpath KH132A between points A1 and A2 | New footpath between points A1 and A3 |
Footpath KH198 between points C1, C2 and C3 | New footpath between points C1, C4, C3 and C5 | |
Hospital Road (D971) between points D1 and D2 | Work No. 14E | |
Borough of Maidstone, Parish of Broomfield | Footpath KH201 between points A1, A2 and A3 | Works Nos. 14F and 14G and new footpath between points A1, A4 and A5 |
Borough of Maidstone, Parishes of Broomfield and Hollingbourne | Greenway Court Road (D946) between points E1 and E2 | Works Nos. 14F and 14G |
Borough of Maidstone, Parishes of Broomfield and Harrietsham | A20 (Ashford Road) between points B1 and B2 | Work No. 14F |
Borough of Maidstone, Parish of Harrietsham | Footpath KH343 between points A1 and A5 | New footpaths between points A1, A2 and A4 and between points A2 and A3 |
Bridleway between points C1 and C2 | New bridleway between those points | |
Footpath KH272 between points E1, E2, E3 and E4 | New footpaths between points E1, E5 and E4 and between points E1 and E6 | |
Footpath KH272A between points F1, F2 and F3 | New footpath between points F1, F4 and F5 | |
Access road between points G1 and G2 | Work No. 14J | |
Borough of Maidstone, Parish of Lenham | Footpath KH416 between points A1 and A2 | New footpath between points A1 and A3 |
Sandway Road (C92) between points C1 and C2 | Work No. 14L | |
Footpath KH414B between points D1 and D2 | Work No. 14L and new footpaths between points D3 and D1 and between points D4 and D5 | |
Old Ham Lane (D986) between points E1 and E2 | Work No. 14M | |
Footpath KH415 between points F3, F1 and F2 | New footpath between points F4 and F5 | |
Borough of Maidstone, Parishes of Boughton Malherbe and Lenham | Lenham Heath Road (C92) between points J1 and J2 | Work No. 14Q |
Lenham Heath Road (C92) between points K1 and K2 | Work No. 14R | |
Bowley Lane between points L1 and L2 | Work No. 14S | |
Borough of Maidstone, Parish of Lenham | Access road to Water Street Cottage between points M1 and M2 | Works Nos. 14U and 14V |
Hook Street between points P1 and P2 | Works Nos. 14U and 14V | |
Footpath KH408A between points Q1, Q2, Q3 and Q4 | New footpath between points Q1 and Q4 | |
Footpath KH407A between points R1 and R2 | New footpath between points R1, R3, R4 and R2 | |
Borough of Ashford, Parish of Charing | Bridleway AW58 between points D1, D2 and C3 and footpath AW17 between points C1 and C3 | New bridleway and footpath between points D1, C1 and D3 |
Hurst Lane (D1198) between points E1 and E2 | Works Nos. 15E and 15F | |
Newlands Road (D1199) between points F1 and F2 | Work No. 15F | |
Footpath AW30 between points G1 and G2 | New footpath between points G3 and G2 | |
Borough of Ashford, Parishes of Charing and Little Chart | Leacon Lane (D1220) between points J1 and J2 and between points J3 and J4 | Work No. 15H |
Borough of Ashford, Parish of Charing | Footpath AW44 between points L1 and L2 | New footpath between points L3, L4 and L2 |
Footpath AW40 between points M1 and M2 | New footpath between points M1, M3 and M2 | |
Borough of Ashford, Parishes of Charing, Hothfield and Westwell | A20 (Maidstone Road) at West Leacon between points P1 and P2 and between points P3 and P4 | Works Nos. 15K and 15L |
Borough of Ashford, Parish of Westwell | Westwell Lane (D1227) between points B1 and B2 | Work No. 15M |
Footpath AW123 between points A1 and A2 | Work No.15M and new footpath between points A1 and A3 | |
Footpath AW124 between points C1, C2 and C3 | Works Nos. 15M and 15N and new footpath between points C4 and C5 | |
Footpath AW124 between points E1, E2 and E3 | New footpath between points E1 and E3 | |
Borough of Ashford, Parishes of Hothfield and Westwell | A20 (Maidstone Road) at Yonsea between points F1 and F2 | Work No. 15P |
Borough of Ashford, Parish of Hothfield | Byway AW173 between points A1, A2 and A3 | New byway between points A4 and A3 |
Borough of Ashford, Parish of Hothfield and Town of Ashford | Godinton Lane (C154) between points B1 and B2 | Work No. 15Q |
Borough of Ashford, Town of Ashford | Footpath AU67 between points A1 and A2 | New footpath between points A1 and A3 |
Godinton Road (B2074) between points C1 and C2 | Works Nos. 16G and 16H | |
Carlton Road (E1467) between points C4 and C5 | Work No. 16G | |
Footpath AU34 between points D1, D2 and D6 | New footpath between points D1, D3, D4, D5 and D6 | |
Footpath AU37 between points F1 and F2 | Work No. 16M | |
Beaver Road (A2070) between points G1 and G2 | Work No. 16N | |
Footpath AU52 between points J1 and J2 | New footpath between points J1, J3, J4, J5 and J2 | |
Boys Hall Road and Canterbury Road (E1466) between points P1 and P2 | Work No. 16QQ | |
Footpath AU51 between points Q1 and Q2 | Work No. 16RR(1) and Work No. 16RR between its junction with Work No. 16RR(1) and point Q2 | |
Crowbridge Road (D4488) between points N1 and N2 | Work No. 16RR(1) and Work No. 16RR between its commencement and its junction with Work No. 16RR(1) | |
Borough of Ashford, Parish of Sevington | Footpath AE341 between points A1 and A2 | New footpath between points A1 and A5 |
Footpath AE343 between points A2, A7 and A3 | New footpath between points A5, A6 and A3 | |
Footpath AE342 between points A2 and A4 | New footpath between points A5 and A8 | |
Highfield Lane between points B5, B4, B6 and B7 and between points B8 and B9 | Works Nos. 17B, 17C and 17C(1) | |
Borough of Ashford, Parishes of Sevington and Mersham | Footpath AE344 between points C1 and C2 and footpath AE364 between points C2, C4 and C5 | New footpath between points C6, C7, C8, C9, C3 and C5 |
Borough of Ashford, Parish of Mersham | Church Road (C177) between points B1 and B2 and between points B3 and B4 | Works Nos. 17F and 17G |
Footpath AE369 between points D1 and D2 | New footpath between points D1 and D3 | |
Borough of Ashford, Parishes of Mersham and Smeeth | Footpath AE373 between points E1 and E2 | New footpath between points E1, E3 and E2 |
Borough of Ashford, Parish of Smeeth | Footpath AE428 between points A1, A2 and A3 and footpath AE430 between points A2 and A4 | New footpath between points A3, A5, A1 and A4 |
Station Road (B2069) between points B1 and B2 | Work No. 17H | |
Footpath AE435 between points C1 and C8 | New footpath between points C1, C3, and C4 | |
Footpath AE437 between points C7 and C5 | New footpath between points C7, C6, C4 and C5 | |
Borough of Ashford, Parish of Aldington | Church Lane (B1424) between points E1 and E2 | Work No. 17K |
District of Shepway, Parish of Sellindge | Footpath HE309 between points A1, A3 and A4 | New footpath between points A1, A2 and A4 |
Bridleway HE271A between points C1, C2 and C3 | New bridleway between points C1 and C4 and new footpath between points C1, C2 and C3 | |
District of Shepway, Parish of Stanford | Footpath HE274 between points A1, A2 and A4 | New footpath between points A1 and A4 |
District of Shepway, Parishes of Postling, Saltwood and Stanford | Footpath HE227 between points B3, C1, C2, C3 and C4 | Work No.17N and new footpaths between points B3, B4 and C5 and between points C6 and C4 |
District of Shepway, Parishes of Postling and Saltwood | A20 (Ashford Road) between points B1 and B2 | Work No. 17Q and new footpath between points B3, B4 and B5 |
District of Shepway, Parish of Saltwood | Footpath HE294 between points A1 and A2 | Work No. 18H and new footpath between points A1 and A3 |
Footpath HE280 between points C1, C2 and C3 | New footpath between points C4 and C5 | |
Footpath HE349 between points C3, C10, C6 and C7 | New footpath between points C8, C9 and C7 | |
Bridleway HE350 between points C11 and C12 | New bridleway between points C12 and C8 |
Modifications etc. (not altering text)
C1Power conferred by Sch. 3 para. 1 ceased to have effect (19.2.1999) by S.I. 1999/537, art. 16
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: