1

The nominated undertaker may, in connection with the construction of the scheduled work or works specified in column (1) of the following table (or any works which are necessary or expedient for the purposes of or in connection with that work or those works)—

a

enter upon and take possession of the land specified in relation to that work or those works in columns (2) and (3) of that table for such purposes as are so specified in column (4) of that table, and

b

for such purposes as are so specified—

i

remove from the land any structure or vegetation, and

ii

construct on the land temporary works (including the provision of means of access) and structures.

Table

(1)

(2)

(3)

(4)

Works

Area

Number of land shown on deposited plans

Purpose for which temporary possession may be taken

GREATER LONDON

1A, 1B, 1C, 1D, 1F and 5D(1)

London Borough of Camden

79

The provision of access for construction purposes.

1A, 1B, 1C, 1D and 1F

87

The provision of a working site and access for construction purposes.

1A, 1AA, 1B, 1BB, 1C, 1CC, 1D, 1DD, 1EE, 1K, 3, 3B, 3C and 5A

182 and 189 to 192

The provision of access for construction purposes.

1HH, 3B and 3C

203 and 204

The provision of access for construction purposes.

1JJ, 2AA and 2BB

London Borough of Islington

782 and 1050

The provision of access for construction purposes.

1AA, 1BB and 3E

787 and 788

The provision of access for construction purposes.

6

London Borough of Hackney

778 and 779

The provision of barge moorings and barge loading facilities.

6

780

The provision of barge loading facilities, spoil handling plant and machinery, a temporary shaft to Work No. 6, a working site and access for construction purposes.

6

781 and 782

The provision of access for construction purposes.

22

London Borough of Newham

1237 and 1239

The provision of a working site.

6, 6A, 6B, 6C, 6D, 6G, 6H, 6J and 7

1253 and 1254

The provision of barge moorings and barge loading facilities, spoil handling plant and machinery, a conveyor, a working site and access for construction purposes.

6, 6A, 6B, 6C, 6D, 6G, 6H, 6J and 7

1255 to 1260

The provision of spoil handling plant and machinery, a conveyor and access for construction purposes.

6, 6A, 6B, 6C, 6D, 6G, 6H, 6J and 7

1261

The provision of spoil handling plant and machinery and a conveyor.

6, 6A, 6B, 6C, 6D, 6G, 6H, 6J and 7

1262 and 1263

The provision of access for construction purposes.

6, 6A, 6B, 6C, 6D, 6G, 6H, 6J and 7

1269

The provision of a working site and access for construction purposes.

6D and 6E

London Borough of Waltham Forest

6

The provision of access for construction purposes.

6D and 6E

10

The provision of access for construction of drainage works.

8Q

London Borough of Barking and Dagenham

205

The provision of access for construction purposes.

8H, 8P(3) and 8P(4)

195, 201 and 202

The provision of access for construction purposes.

8L and 8R

215 and 226

The provision of accesses for construction purposes.

8, 8G, 8J and 8R

217 to 219

The provision of access for construction purposes.

22, 22A, 22B, 22C, 22E, 22F, 22G, 22J and 8U(13)

829 and 830

The provision of a conveyor, spoil handling plant and machinery, and access for construction purposes.

22, 22A, 22B, 22C, 22E, 22F, 22G, 22J and 8U(13)

839

The use of a jetty and provision of moorings in the River Thames.

8, 8G, 8J and 8R

London Borough of Havering

1 to 4

The provision of access for construction purposes.

8 and 8S

25 to 30 and 45

The provision of a working site and access for construction purposes.

8 and 8U(7)

55 and 56

The provision of access for construction purposes.

COUNTY OF ESSEX

9

Borough of Thurrock

52 and 56 to 67

The provision of access for construction purposes.

9, 9C, 9D, 9F(1) and 10

81, 83, 84, 89, 93, 94, 96 and 98

The provision of a working site and access for construction purposes.

COUNTY OF KENT

10, 10A, 10B, 10C and 10J

Borough of Dartford, Parish of Swanscombe and Greenhithe

13 and 14

The provision of access for construction purposes.

10B, 10D, 10F(1) and 10R(2)

21 to 23

The provision of access for construction purposes.

10, 10T(1), 10T(3), 10T(8), 10R, 10P, 10Q and 11 to 11F

Borough of Dartford, Parish of Southfleet

12 and 13

The provision of access for construction purposes.

10T(6), 10T(7) and 10T(8)

26

The provision of access for construction purposes.

11

53

The provision of a working site.

10J and 10J(2)

Borough of Gravesham, Town of Gravesend

2 to 4

The provision of access for construction purposes.

10, 10B, 10C, 10D, 10E and 10F(1)

12 to 14

The provision of access for construction purposes.

10R(2)

42

The provision of access for construction purposes.

10B, 10C and 10N

70

The provision of access for construction purposes.

12, 12F and 12H

Borough of Gravesham, Parish of Cobham

28

The provision of a working site and temporary road diversion.

20A and 20B

Borough of Gravesham, Parish of Higham

9 and 10

The provision of access to a railhead to be used for construction purposes.

20A and 20B

Borough of Gravesham, Parish of Shorne

18

The provision of access to a railhead to be used for construction purposes.

13, 13B

City of Rochester Upon Medway, Town of Rochester

27 to 29

The provision of a working site and access to the River Medway for construction purposes.

13C and 13D

65, 68, 69 and 71

The provision of access for construction purposes.

13C and 13D

Borough of Tonbridge and Malling, Parish of Wouldham

1 and 2

The provision of access for construction purposes.

13

Borough of Tonbridge and Malling, Parish of Aylesford

1, 4, 29 and 41

The provision of a working site and access for construction purposes.

13

Borough of Maidstone, Parish of Boxley

88

The provision of access for construction purposes.

13 and 13J

Borough of Maidstone, Parish of Detling

1

The provision of a working site and access for construction purposes.

14 and 14A

Borough of Maidstone, Parish of Thurnham

5

The provision of a working site and access for construction purposes.

14

Borough of Maidstone, Parish of Leeds

1

The provision of access for construction purposes.

15

Borough of Ashford, Parish of Hothfield

6

The provision of access for construction purposes.

16, 16A, 16B and 16F

15

The provision of a working site and access for construction purposes.

16, 16A and 16B

Borough of Ashford, Town of Ashford

16

The provision of a working site.

16C and 16H

34 to 37 and 48

The provision of a working site and access for construction purposes.

16 and 16H

59 to 73 and 76

The provision of a working site and access for construction purposes.

16 and 16K

78

The provision of a working site and access for construction purposes.

16A, 16B, 16C, 16K and 16L

46 and 78 to 80

The provision of a working site and access for construction purposes.

16, 16A, 16B, 16C, 16K and 16M

85, 86, 89, 94 and 95

The provision of a working site and access for construction purposes.

16, 16A, 16B 16C and 16D

110, 111, 117 and 122

The provision of a working site and access for construction purposes.

16, 16A, 16B, 16C, 16D and 16E

125 and 131

The provision of a working site and access for construction purposes.

17, 17B and 17C

Borough of Ashford, Parish of Sevington

28

The provision of a working site.

17 and 17H

Borough of Ashford, Parish of Smeeth

24 and 27

The provision of access for construction purposes.

17, 17J(1) and 17K

31

The provision of a working site and access for construction purposes.

17 and 17J(2)

District of Shepway, Parish of Sellindge

44, 45 and 60

The provision of access for construction purposes.

17

District of Shepway, Parish of Stanford

7 and 17 to 19

The provision of access for construction purposes.

17 and 17Q

District of Shepway, Parish of Saltwood

13 to 16

The provision of a working site and access for construction purposes.

17, 17Q and 17P

District of Shepway, Parish of Postling

11 and 14 to 18

The provision of a working site and access for construction purposes.

18B, 18E, 18F and 18G

District of Shepway, Parish of Newington

3 and 4

The provision of a working site and access for construction purposes.

18J

6 and 9

The provision of access for construction purposes.

18A, 18AA, 18B, 18F, 18G and 18K

14 to 16, 19 to 21, 32 and 37

The provision of a working site and access for construction purposes.

18A, 18AA, 18B and 18G

31 and 40

The provision of working sites and access for construction purposes.

18AA

62

The provision of access for construction purposes.

18E

District of Shepway, Parish of Hythe

1

The provision of access for construction purposes.

18AA

District of Shepway, Town of Folkestone

6

The provision of a working site and access for construction purposes.

13, 14, 15, 15A, 15B, 16, 16A, 16B, 16C, 16D, 16E, 17, 18A, 18AA, 18B, 18C, 18D, 18F, 18G and all railway works associated therewith

District of Thanet, Parish of Minster

2

The provision of access to a railhead to be used for construction purposes.

13, 14, 15, 15A, 15B, 16, 16A, 16B, 16C, 16D, 16E, 17, 18A, 18AA, 18B, 18C, 18D, 18F, 18G and all railway works associated therewith

District of Dover, Parish of Sandwich

1

The provision of access to a railhead to be used for construction purposes.

2

Not less than 28 days before entering upon and taking possession of land under this paragraph, the nominated undertaker shall give notice to the owners and occupiers of the land of its intention to do so.

3

The nominated undertaker may not remain in possession of any land under this paragraph after the end of the period of one year beginning with the date of completion of the work or works specified in relation to the land in column (1) of the table in sub-paragraph (1) above unless the owners of the land agree.

4

The nominated undertaker shall pay compensation to the owners and occupiers of land of which possession is taken under this paragraph for any loss which they may suffer by reason of the exercise in relation to the land of the powers conferred by this paragraph.

5

Any dispute as to a person’s entitlement to compensation under sub-paragraph (4) above, or as to the amount of compensation, shall be determined under and in accordance with Part I of the M1Land Compensation Act 1961.

6

Nothing in this paragraph shall affect any liability to pay compensation under section 10(2) of the M2Compulsory Purchase Act 1965, as applied to the acquisition of land under section 4(1) above, or under any other enactment, otherwise than for loss for which compensation is payable under sub-paragraph (4) above.

7

In this paragraph, “structure” includes any erection.

2

1

Before giving up possession of land of which possession has been taken under paragraph 1 above, the nominated undertaker shall, in accordance with a scheme agreed with the owners of the land and the relevant planning authority, put the land into such condition as the scheme may provide.

2

If, in relation to any land of which possession has been taken under paragraph 1 above, no scheme has been agreed for the purposes of this paragraph within 6 months of the date of completion of the work or works specified in relation to the land in column (1) of the table in paragraph 1(1) above, the scheme shall be such as may be determined by the F1Secretary of State after consultation with the nominated undertaker, the owners of the land and the relevant planning authority.

3

Unless the owners of the land and the nominated undertaker otherwise agree, a scheme determined under sub-paragraph (2) above shall provide for land to be restored to its former condition.

4

Unless the nominated undertaker otherwise agrees, a scheme determined under sub-paragraph (2) above shall not provide for the nominated undertaker to replace any structure removed under paragraph 1 above other than a fence.

5

Where the F2Secretary of State asks the relevant planning authority for assistance in connection with the carrying out by F2him of his function under sub-paragraph (2) above, F2he may require the nominated undertaker to reimburse to the planning authority any expenses which it reasonably incurs in meeting the request.

6

The duty under sub-paragraph (1) above in relation to any land shall be owed separately to the owners of the land and to the relevant planning authority.

7

Where a scheme for the purposes of this paragraph provides for any step to be taken by the nominated undertaker before a specified date and that step has not been taken before that date, the relevant planning authority may—

a

enter the land concerned and take that step, and

b

require the nominated undertaker to reimburse to it any expenses which it reasonably incurs in acting under paragraph (a) above.

8

In this paragraph—

  • F3. . .

  • relevant planning authority” means—

    1. a

      in relation to Greater London, the local planning authority, and

    2. b

      in relation to Essex or Kent, the district planning authority; and

  • structure” includes any erection.

3

1

Where the power under paragraph 1 above to take possession of land is exercised in relation to any land to which section 4(1) above applies, the relevant powers of compulsory acquisition shall thereupon cease to be exercisable in relation to that land.

2

Sub-paragraph (1) above shall not apply to compulsory acquisition by virtue of paragraph 8(1) of Schedule 4 to this Act.

3

In sub-paragraph (1) above, the reference to the relevant powers of compulsory acquisition is to—

a

the power to serve a notice to treat under Part I of the M3Compulsory Purchase Act 1965, as applied to the acquisition of land under section 4(1) above, and

b

the power to execute a declaration under section 4 of the M4Compulsory Purchase (Vesting Declarations) Act 1981, as applied by paragraph 4 of Schedule 4 to this Act.

Occupation and use for maintenance of works

C14

1

At any time during the maintenance period relating to any of the scheduled works, the nominated undertaker may—

a

enter upon and take possession of any land which is—

i

within 20 metres from that work, and

ii

within the limits of deviation for the scheduled works or the limits of land to be acquired or used,

if such possession is reasonably required for the purpose of or in connection with maintaining the work or any ancillary works connected with it, and

b

construct on the land such temporary works (including the provision of means of access) and structures as may be reasonably so required.

2

Sub-paragraph (1) above shall not authorise the nominated undertaker to take possession of—

a

a house,

b

any other structure which is for the time being occupied, or

c

a garden belonging to a house.

3

Not less than 28 days before entering upon and taking possession of land under this paragraph, the nominated undertaker shall give notice to the owners and occupiers of the land of its intention to do so.

4

The nominated undertaker may only remain in possession of land under this paragraph for so long as may be reasonably required to carry out the maintenance works for which possession of the land was taken.

5

Before giving up possession of land of which possession has been taken under this paragraph, the nominated undertaker shall restore the land to the reasonable satisfaction of the owners of the land.

6

The nominated undertaker shall pay compensation to the owners and occupiers of land of which possession is taken under this paragraph for any loss which they may suffer by reason of the exercise in relation to the land of the powers conferred by this paragraph.

7

Any dispute as to a person’s entitlement to compensation under sub-paragraph (6) above, or as to the amount of the compensation, shall be determined under and in accordance with Part I of the M5Land Compensation Act 1961.

8

Nothing in this paragraph shall affect any liability to pay compensation under section 10(2) of the M6Compulsory Purchase Act 1965, as applied to the acquisition of land under section 4(1) above, or under any other enactment, otherwise than for loss for which compensation is payable under sub-paragraph (6) above.

9

In this paragraph—

a

the maintenance period”, in relation to any work, means the period beginning with the date on which the work is completed and ending 5 years after the date on which it is brought into general use,

b

structure” includes any erection, and

c

any reference to land within a specified distance of a work includes, in the case of a work under the surface of the ground, a reference to land within the specified distance of any point on the surface below which the work is situated.

Suspension of private rights of way

C25

1

All private rights of way over land of which the nominated undertaker takes possession under paragraph 1 or 4 above shall be suspended and unenforceable for as long as it remains in lawful possession of the land.

2

Any person who suffers loss by the suspension of any right under this paragraph shall be entitled to compensation.

3

Any dispute as to a person’s entitlement to compensation under this paragraph, or as to the amount of such compensation, shall be determined under and in accordance with Part I of the Land Compensation Act 1961.