Print Options
PrintThe Whole
Act
PrintThe Whole
Schedule
PrintThe Whole
Part
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Paragraph 29


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 18/12/1996.
Changes to legislation:
There are currently no known outstanding effects for the Channel Tunnel Rail Link Act 1996, Paragraph 29.

Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
29(1)Where a planning authority considers that a request for approval under Part II or III of this Schedule relates to matters which may affect the Lee Valley Regional Park, it shall, within 5 days of receiving the request, invite the Lee Valley Regional Park Authority to make representations.U.K.
(2)Where under sub-paragraph (1) above a planning authority has invited the Lee Valley Regional Park Authority to make representations about a request for approval under Part II or III of this Schedule, it shall not make any decision about the request until—
(a)it has received representations from the Authority about the request,
(b)it has been informed by the Authority that it does not wish to make any representations about the request, or
(c)21 days have elapsed since the date of the invitation.
(3)An invitation under sub-paragraph (1) above shall specify the time limit for making representations.